Oldest supporting observation: 2026-10-18T21:58:06.097601+00:00
Dossier released: 2026-10-18T22:38:39.616038+00:00
Source report dates and capture dates are listed per fact below; neither establishes an event date.

## Project summary

A Port of Oakland update dated July 30, 2026, describes four electric ship-to-shore cranes at TraPac’s Oakland terminal. It reports that the first two had been commissioned and were operational, while the remaining two were still being built and were expected to enter service in Fall 2026. The article identifies Liebherr as manufacturer and Pacific Crane Maintenance Company as on-site assembler.

## Evidence limits and unknowns

- The July 2026 article does not state project cost, financing amount, or procurement route, or identify a supplier opportunity. It also does not establish the later status of the two cranes expected to enter service in Fall 2026.

Current purchasing availability: unknown.
Source-dated plans do not establish current progress or available supplier packages.

## Project metadata

Country: United States
Region: North America
Physical assets: Seaport
Derived from the exact released evidence; unresolved fields remain unclassified.

## Project category

Transport and logistics
Derived from the reviewed scope statement; delivery stage remains unclassified.
Four new 100%-electric Liebherr ship-to-shore cranes, manufactured in Ireland; each is reported as 440+ feet tall, designed to reach 24 container rows and work stacks up to 11 containers high. Two were reported in service/fully operational; the other two were under construction or assembly and expected to be operational in Fall 2026.
Source: www.portofoakland.com — https://www.portofoakland.com/port-of-oakland-and-trapac-celebrate-new-electric-cranes | published unknown | observed 2026-10-18T21:58:06.097601+00:00

Project overview
Oldest decisive evidence: 2026-10-18T21:58:06.097601+00:00
Newest evidence: 2026-10-18T21:58:06.097601+00:00
Knowledge reviewed: 2026-10-18T22:33:57.555453+00:00
Publication reviewed: 2026-10-18T22:35:41.920853+00:00

## Date
The page is dated July 30, 2026, and the article text carries a July 28, 2026 dateline. Crane sections arrived in January 2026; a time-lapse documents construction from April–June 2026; commissioning of the first two cranes was celebrated on July 7.
Status: reported
Attribution: www.portofoakland.com
Source: www.portofoakland.com — https://www.portofoakland.com/port-of-oakland-and-trapac-celebrate-new-electric-cranes | published unknown | observed 2026-10-18T21:58:06.097601+00:00

## Name
Oakland TraPac electric crane phase: four new ship-to-shore cranes at TraPac’s Oakland terminal.
Status: reported
Attribution: www.portofoakland.com
Source: www.portofoakland.com — https://www.portofoakland.com/port-of-oakland-and-trapac-celebrate-new-electric-cranes | published unknown | observed 2026-10-18T21:58:06.097601+00:00

## Scope
Four new 100%-electric Liebherr ship-to-shore cranes, manufactured in Ireland; each is reported as 440+ feet tall, designed to reach 24 container rows and work stacks up to 11 containers high. Two were reported in service/fully operational; the other two were under construction or assembly and expected to be operational in Fall 2026.
Status: reported
Attribution: www.portofoakland.com
Source: www.portofoakland.com — https://www.portofoakland.com/port-of-oakland-and-trapac-celebrate-new-electric-cranes | published unknown | observed 2026-10-18T21:58:06.097601+00:00

## Location
TraPac Terminal, Port of Oakland, Oakland, California.
Status: reported
Attribution: www.portofoakland.com
Source: www.portofoakland.com — https://www.portofoakland.com/port-of-oakland-and-trapac-celebrate-new-electric-cranes | published unknown | observed 2026-10-18T21:58:06.097601+00:00


## Cite this dossier

CapexCue — Oakland TraPac electric crane phase: four new ship-to-shore cranes at TraPac’s Oakland terminal. — dossier released 2026-10-18T22:38:39.616038+00:00, release 1 (7a639888-f0c2-4b05-b4b3-cf44f83009fb) — https://capexcue.com/projects/oakland-trapac-electric-crane-phase-four-new-ship-to-shore-cranes-at-trapacs-oakland-terminal-9d99df58-e14/.

For current information and later dossier updates, visit <https://capexcue.com/projects/oakland-trapac-electric-crane-phase-four-new-ship-to-shore-cranes-at-trapacs-oakland-terminal-9d99df58-e14/>.
This file records the release identified above; the current dossier may change.