# Botley West Solar Farm

Publisher: CapexCue
Canonical dossier: <https://capexcue.com/projects/rr22-botley-west/>
Dossier reference: release 1 (7ba50403-5880-44d8-83d6-5a9c542ef038)

Released project intelligence

Oldest supporting observation: 2026-10-01T02:16:06.518112+00:00
Dossier released: 2026-10-16T15:38:49.136096+00:00
Source report dates and capture dates are listed per fact below; neither establishes an event date.

## Project summary

Botley West Solar Farm is a planned solar photovoltaic array and connection project, with a maximum intended generation capacity of 840MW, across approximately 1,400 hectares in West Oxfordshire, Cherwell and Vale of White Horse districts. The project information observed on 1 October 2026 reported it at the decision stage, with completion set for 10 November 2026. This does not establish that a decision has been made or that construction has begun.

## Evidence limits and unknowns

- Only the supplied project-information text was reviewed; this was not a review of the complete source document.
- Email-containing and link-only paragraphs, linked documents and graphical content were not reviewed.
- Later project progress and procurement availability are not established.

Current purchasing availability: unknown.
Source-dated plans do not establish current progress or available supplier packages.

## Project metadata

Country: United Kingdom
Region: Europe
Physical assets: Solar PV
Derived from the exact released evidence; unresolved fields remain unclassified.

## Project category

Energy
Derived from the reviewed scope statement; delivery stage remains unclassified.
Solar photovoltaic array and connection infrastructure, with a maximum intended generation capacity of 840MW.
Source: Planning Inspectorate — https://national-infrastructure-consenting.planninginspectorate.gov.uk/projects/EN010147 | published unknown | observed 2026-10-01T02:16:06.518112+00:00

Project overview
Oldest decisive evidence: 2026-10-01T02:16:06.518112+00:00
Newest evidence: 2026-10-01T02:16:06.518112+00:00
Knowledge reviewed: 2026-10-16T15:38:48.795211+00:00
Publication reviewed: 2026-10-16T15:38:48.795211+00:00

## Name
Botley West Solar Farm
Status: reported
Attribution: Planning Inspectorate
Source: Planning Inspectorate — https://national-infrastructure-consenting.planninginspectorate.gov.uk/projects/EN010147 | published unknown | observed 2026-10-01T02:16:06.518112+00:00

## Scope
Solar photovoltaic array and connection infrastructure, with a maximum intended generation capacity of 840MW.
Status: planned
Attribution: Planning Inspectorate
Source: Planning Inspectorate — https://national-infrastructure-consenting.planninginspectorate.gov.uk/projects/EN010147 | published unknown | observed 2026-10-01T02:16:06.518112+00:00

## Delivery
This project is at the decision stage. The date set for this to be completed is 10 November 2026
Status: reported
Attribution: Planning Inspectorate
Source: Planning Inspectorate — https://national-infrastructure-consenting.planninginspectorate.gov.uk/projects/EN010147 | published unknown | observed 2026-10-01T02:16:06.518112+00:00

## Location
Land in West Oxfordshire, Cherwell and Vale of White Horse Districts, across approx 1400 hectares
Status: reported
Attribution: Planning Inspectorate
Source: Planning Inspectorate — https://national-infrastructure-consenting.planninginspectorate.gov.uk/projects/EN010147 | published unknown | observed 2026-10-01T02:16:06.518112+00:00


## Cite this dossier

CapexCue — Botley West Solar Farm — dossier released 2026-10-16T15:38:49.136096+00:00, release 1 (7ba50403-5880-44d8-83d6-5a9c542ef038) — https://capexcue.com/projects/rr22-botley-west/.

For current information and later dossier updates, visit <https://capexcue.com/projects/rr22-botley-west/>.
This file records the release identified above; the current dossier may change.