# Lighthouse Green Fuels Project

Publisher: CapexCue
Canonical dossier: <https://capexcue.com/projects/lighthouse-green-fuels-project-379ecd19ae13b094/>
Dossier reference: release 1 (9daab6af-3628-4f14-a38e-b1f351660cd0)

Released project intelligence

Oldest supporting observation: 2026-10-01T02:15:46.856664+00:00
Dossier released: 2026-10-15T16:08:37.342764+00:00
Source report dates and capture dates are listed per fact below; neither establishes an event date.

## Project summary

The Lighthouse Green Fuels Project is a proposed SAF production development with processing, storage, export and utility infrastructure. Its described scope includes a biomass-fired CHP plant with electrical output up to approximately 200 MWe and additional steam for SAF production. The proposed Main Site is on the north bank of the River Tees, south of Seal Sands Road, in Stockton-on-Tees and Redcar and Cleveland, Teesside. The displayed boundaries are illustrative; the page directs readers to relevant plans and drawings for exact boundaries.

The Planning Inspectorate’s update dated 30 September 2026 says the application had been received on 21 September and was at the acceptance stage. A decision on acceptance was due by 19 October 2026; the page does not confirm that it was accepted. Comments were not available at that stage. The page names LGF Projects Limited as applicant, but does not identify it as the developer; it includes a link labelled as the developer’s website.

## Evidence limits and unknowns

- The supplied page does not report the outcome of the acceptance decision; the stated 19 October 2026 deadline is not confirmation of acceptance.
- Exact project boundaries are not established in the supplied text; the page describes displayed boundaries as illustrative and refers readers to relevant plans and drawings.
- The developer’s identity is not established by the supplied text. It identifies LGF Projects Limited as applicant and includes a developer-website link, but the linked page was not acquired or interpreted.
- Financing, procurement arrangements, contract packages and purchasing timing are not stated in the project-information content supplied.
- The supplied text does not expressly state the country.

Current purchasing availability: unknown.
Source-dated plans do not establish current progress or available supplier packages.

## Project metadata

Country: United Kingdom
Region: Europe
Physical assets: Not classified
Derived from the exact released evidence; unresolved fields remain unclassified.

## Project category

Energy
Derived from the reviewed scope statement; delivery stage remains unclassified.
The described development comprises the SAF production, pre-treatment, processing and storage plant; marine infrastructure and pipelines for exporting finished product to marine or rail loading infrastructure; a biomass-fired CHP plant with electrical output up to approximately 200 MWe and additional steam production; utility pipelines, wastewater treatment and discharge, an electricity connection, an air separation unit, bulk storage for feedstock, intermediates and product, and associated and ancillary infrastructure.
Source: Planning Inspectorate — https://national-infrastructure-consenting.planninginspectorate.gov.uk/projects/EN0110025 | published unknown | observed 2026-10-01T02:15:46.856664+00:00

Project overview
Oldest decisive evidence: 2026-10-01T02:15:46.856664+00:00
Newest evidence: 2026-10-01T02:15:46.856664+00:00
Knowledge reviewed: 2026-10-15T16:08:37.090467+00:00
Publication reviewed: 2026-10-15T16:08:37.090467+00:00

## Name
Lighthouse Green Fuels Project
Status: reported
Attribution: Planning Inspectorate
Source: Planning Inspectorate — https://national-infrastructure-consenting.planninginspectorate.gov.uk/projects/EN0110025 | published unknown | observed 2026-10-01T02:15:46.856664+00:00

## Scope
The described development comprises the SAF production, pre-treatment, processing and storage plant; marine infrastructure and pipelines for exporting finished product to marine or rail loading infrastructure; a biomass-fired CHP plant with electrical output up to approximately 200 MWe and additional steam production; utility pipelines, wastewater treatment and discharge, an electricity connection, an air separation unit, bulk storage for feedstock, intermediates and product, and associated and ancillary infrastructure.
Status: planned
Attribution: Planning Inspectorate
Source: Planning Inspectorate — https://national-infrastructure-consenting.planninginspectorate.gov.uk/projects/EN0110025 | published unknown | observed 2026-10-01T02:15:46.856664+00:00

## Location
The project land is described as being in the boroughs of Stockton-on-Tees and Redcar and Cleveland, Teesside. The proposed Main Site is on the north bank of the River Tees, south of Seal Sands Road. The page says displayed boundaries are illustrative and points to the latest relevant plans and drawings for exact boundaries.
Status: planned
Attribution: Planning Inspectorate
Source: Planning Inspectorate — https://national-infrastructure-consenting.planninginspectorate.gov.uk/projects/EN0110025 | published unknown | observed 2026-10-01T02:15:46.856664+00:00

## Developer
The supplied text does not identify the developer. It contains a link labelled “View the developer's website,” but the linked page was not acquired or interpreted.
Status: reported
Attribution: Planning Inspectorate
Source: Planning Inspectorate — https://national-infrastructure-consenting.planninginspectorate.gov.uk/projects/EN0110025 | published unknown | observed 2026-10-01T02:15:46.856664+00:00

## Regulatory
The page identifies the application type as “Generating Stations.” It reports that the application was received on 21 September 2026 and that the project was at the acceptance stage as of the latest update. Comments were not available at that stage; receipt of the application does not mean it had been accepted for examination.
Status: reported
Attribution: Planning Inspectorate
Source: Planning Inspectorate — https://national-infrastructure-consenting.planninginspectorate.gov.uk/projects/EN0110025 | published unknown | observed 2026-10-01T02:15:46.856664+00:00

## Next Milestone
A decision on whether to accept the application for examination was due by 19 October 2026. This is a stated deadline, not evidence that the application was accepted.
Status: planned
Attribution: Planning Inspectorate
Source: Planning Inspectorate — https://national-infrastructure-consenting.planninginspectorate.gov.uk/projects/EN0110025 | published unknown | observed 2026-10-01T02:15:46.856664+00:00


## Cite this dossier

CapexCue — Lighthouse Green Fuels Project — dossier released 2026-10-15T16:08:37.342764+00:00, release 1 (9daab6af-3628-4f14-a38e-b1f351660cd0) — https://capexcue.com/projects/lighthouse-green-fuels-project-379ecd19ae13b094/.

For current information and later dossier updates, visit <https://capexcue.com/projects/lighthouse-green-fuels-project-379ecd19ae13b094/>.
This file records the release identified above; the current dossier may change.