# Limondale BESS Battery Energy Storage System

Publisher: CapexCue
Canonical dossier: <https://capexcue.com/projects/limondale-bess-battery-energy-storage-system-c48c21df-d7d/>
Dossier reference: release 1 (28b0cb78-0632-4570-aa02-b46d846dff24)

Released project intelligence

Oldest supporting observation: 2026-10-17T10:42:12.837068+00:00
Dossier released: 2026-10-17T11:50:40.092433+00:00
Source report dates and capture dates are listed per fact below; neither establishes an event date.

## Project summary

Limondale BESS is a battery storage project near Balranald, New South Wales, alongside Limondale Solar Farm. The project is described as 50+ MW and 400+ MWh, with an eight-hour duration, and connects through the solar farm’s existing 33 kV substation. The project page lists it as in operation; a May 2026 news item reports its move from commissioning to full operations. The page also reports AEMO registration in September 2025.

## Evidence limits and unknowns

- The supplied page does not state whether procurement or supplier packages are currently available. It lists the project as in operation and includes a May 2026 report of full operations; no open buying window is documented.
- A financing amount is not stated in the supplied material; the page identifies a May 2024 announcement as the investment decision.
- Current supplier package boundaries and detailed equipment requirements are not stated; the page describes the overall battery capacity and grid connection.

Current purchasing availability: unknown.
Source-dated plans do not establish current progress or available supplier packages.

## Project metadata

Country: Australia
Region: Oceania
Physical assets: Battery Storage
Derived from the exact released evidence; unresolved fields remain unclassified.

## Project category

Energy
Derived from the reviewed name statement; delivery stage remains unclassified.
Limondale BESS Battery Energy Storage System
Source: au.rwe.com — https://au.rwe.com/projects/limondale-bess/ | published unknown | observed 2026-10-17T10:42:12.837068+00:00

Project overview
Oldest decisive evidence: 2026-10-17T10:42:12.837068+00:00
Newest evidence: 2026-10-17T10:42:12.837068+00:00
Knowledge reviewed: 2026-10-17T11:49:09.488832+00:00
Publication reviewed: 2026-10-17T11:50:31.356383+00:00

## Name
Limondale BESS Battery Energy Storage System
Status: reported
Attribution: au.rwe.com
Source: au.rwe.com — https://au.rwe.com/projects/limondale-bess/ | published unknown | observed 2026-10-17T10:42:12.837068+00:00

## Scope
Battery energy storage system described as 50+ MW and 400+ MWh, with an eight-hour duration. Designed to store excess solar generation for delivery to the grid; connects through the Limondale Solar Farm’s existing 33 kV substation.
Status: reported
Attribution: au.rwe.com
Source: au.rwe.com — https://au.rwe.com/projects/limondale-bess/ | published unknown | observed 2026-10-17T10:42:12.837068+00:00

## Activity
The project page lists the BESS as in operation; a May 2026 news item says the eight-hour battery moved from commissioning to full operations.
Status: reported
Attribution: au.rwe.com
Source: au.rwe.com — https://au.rwe.com/projects/limondale-bess/ | published unknown | observed 2026-10-17T10:42:12.837068+00:00

## Location
Near Balranald, New South Wales, Australia; adjacent to the existing Limondale Solar Farm.
Status: reported
Attribution: au.rwe.com
Source: au.rwe.com — https://au.rwe.com/projects/limondale-bess/ | published unknown | observed 2026-10-17T10:42:12.837068+00:00

## Investment
A May 2024 media announcement is identified as the BESS investment decision.
Status: reported
Attribution: au.rwe.com
Source: au.rwe.com — https://au.rwe.com/projects/limondale-bess/ | published unknown | observed 2026-10-17T10:42:12.837068+00:00

## Regulatory
Reportedly registered with the Australian Energy Market Operator (AEMO) in September 2025.
Status: actual
Attribution: au.rwe.com
Source: au.rwe.com — https://au.rwe.com/projects/limondale-bess/ | published unknown | observed 2026-10-17T10:42:12.837068+00:00


## Cite this dossier

CapexCue — Limondale BESS Battery Energy Storage System — dossier released 2026-10-17T11:50:40.092433+00:00, release 1 (28b0cb78-0632-4570-aa02-b46d846dff24) — https://capexcue.com/projects/limondale-bess-battery-energy-storage-system-c48c21df-d7d/.

For current information and later dossier updates, visit <https://capexcue.com/projects/limondale-bess-battery-energy-storage-system-c48c21df-d7d/>.
This file records the release identified above; the current dossier may change.