# 50MW/100MWh Bouldercombe Battery Project

Publisher: CapexCue
Canonical dossier: <https://capexcue.com/projects/50mw100mwh-bouldercombe-battery-project-81ed5f5f-219/>
Dossier reference: release 1 (b68fe8c1-e41b-46c3-b457-5610e913121b)

Released project intelligence

Oldest supporting observation: 2026-10-17T14:12:38.028445+00:00
Dossier released: 2026-10-17T14:35:56.026707+00:00
Source report dates and capture dates are listed per fact below; neither establishes an event date.

## Project summary

The Bouldercombe Battery Project is a 50 MW/100 MWh battery energy storage project in Rockhampton, built using Tesla Megapack 2.0 hardware. Genex describes it as operational and reports full commercial operations from 2H CY2023.

## Evidence limits and unknowns

- The supplied page does not document whether a separate expansion, augmentation, replacement, or other procurement is planned, whether any supplier opportunity is open, or buying-window dates.

Current purchasing availability: unknown.
Source-dated plans do not establish current progress or available supplier packages.

## Project metadata

Country: Australia
Region: Oceania
Physical assets: Battery Storage
Derived from the exact released evidence; unresolved fields remain unclassified.

## Project category

Energy
Derived from the reviewed scope statement; delivery stage remains unclassified.
50 MW/100 MWh large-scale battery energy storage project (BESS), built using Tesla Megapack 2.0 hardware.
Source: genexpower.com.au — https://genexpower.com.au/bouldercombe-battery-project/ | published unknown | observed 2026-10-17T14:12:38.028445+00:00

## Project milestones

Project event times are distinct from source publication, observation and dossier release dates. An elapsed plan does not establish completion.

### Project · Commercial operations began
Event time: 2H CY2023 (half-year)
Status: Reported event
Basis: Reviewed activity statement; not a verbatim source quotation.
Released statement reference: released-statement:activity:0:74:commercial_operations_began
Released statement: Described as operational and in full commercial operations from 2H CY2023.
Corroboration: uncorroborated
Limitation: This source report does not establish current progress.
Source: genexpower.com.au — https://genexpower.com.au/bouldercombe-battery-project/ | published unknown | observed 2026-10-17T14:12:38.028445+00:00

Project overview
Oldest decisive evidence: 2026-10-17T14:12:38.028445+00:00
Newest evidence: 2026-10-17T14:12:38.028445+00:00
Knowledge reviewed: 2026-10-17T14:34:12.037528+00:00
Publication reviewed: 2026-10-17T14:35:36.538446+00:00

## Name
50MW/100MWh Bouldercombe Battery Project
Status: reported
Attribution: genexpower.com.au
Source: genexpower.com.au — https://genexpower.com.au/bouldercombe-battery-project/ | published unknown | observed 2026-10-17T14:12:38.028445+00:00

## Scope
50 MW/100 MWh large-scale battery energy storage project (BESS), built using Tesla Megapack 2.0 hardware.
Status: reported
Attribution: genexpower.com.au
Source: genexpower.com.au — https://genexpower.com.au/bouldercombe-battery-project/ | published unknown | observed 2026-10-17T14:12:38.028445+00:00

## Activity
Described as operational and in full commercial operations from 2H CY2023.
Status: actual
Attribution: genexpower.com.au
Source: genexpower.com.au — https://genexpower.com.au/bouldercombe-battery-project/ | published unknown | observed 2026-10-17T14:12:38.028445+00:00

## Location
Rockhampton
Status: reported
Attribution: genexpower.com.au
Source: genexpower.com.au — https://genexpower.com.au/bouldercombe-battery-project/ | published unknown | observed 2026-10-17T14:12:38.028445+00:00


## Cite this dossier

CapexCue — 50MW/100MWh Bouldercombe Battery Project — dossier released 2026-10-17T14:35:56.026707+00:00, release 1 (b68fe8c1-e41b-46c3-b457-5610e913121b) — https://capexcue.com/projects/50mw100mwh-bouldercombe-battery-project-81ed5f5f-219/.

For current information and later dossier updates, visit <https://capexcue.com/projects/50mw100mwh-bouldercombe-battery-project-81ed5f5f-219/>.
This file records the release identified above; the current dossier may change.