# Rumah 1 IPP; also described as the “Rumah-1 Independent Power Project.”

Publisher: CapexCue
Canonical dossier: <https://capexcue.com/projects/rumah-1-ipp-also-described-as-the-rumah-1-independent-power-project-d65a1a35-f17/>
Dossier reference: release 1 (e792fbbf-bc47-4487-af76-1d10b31277d6)

Released project intelligence

Oldest supporting observation: 2026-10-18T07:27:11.032713+00:00
Dossier released: 2026-10-18T07:53:01.450246+00:00
Source report dates and capture dates are listed per fact below; neither establishes an event date.

## Project summary

Rumah 1 IPP is described as a 1,800 MW natural-gas CCGT independent power plant in Riyadh province, Saudi Arabia. ACWA Power is identified as developer; the source reports a 25-year PPA with SPPC and lists Q2 2028 as the planned commercial operations date.

## Evidence limits and unknowns

- The supplied project-page content, observed 2026-10-18, does not state a financing amount or establish current procurement availability or tender status.
- The supplied content does not describe specific equipment packages or their procurement status.

Current purchasing availability: unknown.
Source-dated plans do not establish current progress or available supplier packages.

## Project metadata

Country: Saudi Arabia
Region: Middle East North Africa
Physical assets: Not classified
Derived from the exact released evidence; unresolved fields remain unclassified.

## Project category

Energy
Derived from the reviewed scope statement; delivery stage remains unclassified.
A 1,800 MW combined-cycle gas turbine (CCGT) independent power plant using natural gas.
Source: acwapower.com — https://acwapower.com/en/what-we-do/projects/rumah-1-ipp/ | published unknown | observed 2026-10-18T07:27:11.032713+00:00

Project overview
Oldest decisive evidence: 2026-10-18T07:27:11.032713+00:00
Newest evidence: 2026-10-18T07:27:11.032713+00:00
Knowledge reviewed: 2026-10-18T07:51:31.388785+00:00
Publication reviewed: 2026-10-18T07:52:54.554223+00:00

## Date
Commercial operations date listed as Q2 2028.
Status: planned
Attribution: acwapower.com
Source: acwapower.com — https://acwapower.com/en/what-we-do/projects/rumah-1-ipp/ | published unknown | observed 2026-10-18T07:27:11.032713+00:00

## Name
Rumah 1 IPP; also described as the “Rumah-1 Independent Power Project.”
Status: reported
Attribution: acwapower.com
Source: acwapower.com — https://acwapower.com/en/what-we-do/projects/rumah-1-ipp/ | published unknown | observed 2026-10-18T07:27:11.032713+00:00

## Owner
Reported shareholders: ACWA Power 35%, Saudi Electricity Company (SEC) 35%, and Korea Electric Power Corporation (KEPCO) 30%.
Status: reported
Attribution: acwapower.com
Source: acwapower.com — https://acwapower.com/en/what-we-do/projects/rumah-1-ipp/ | published unknown | observed 2026-10-18T07:27:11.032713+00:00

## Scope
A 1,800 MW combined-cycle gas turbine (CCGT) independent power plant using natural gas.
Status: reported
Attribution: acwapower.com
Source: acwapower.com — https://acwapower.com/en/what-we-do/projects/rumah-1-ipp/ | published unknown | observed 2026-10-18T07:27:11.032713+00:00

## Activity
ACWA Power and Saudi Power Procurement Company (SPPC) are reported to have signed a 25-year power purchase agreement for development, financing, build, own and operate of the plant; SPPC is identified as the sole off-taker.
Status: reported
Attribution: acwapower.com
Source: acwapower.com — https://acwapower.com/en/what-we-do/projects/rumah-1-ipp/ | published unknown | observed 2026-10-18T07:27:11.032713+00:00

## Location
Riyadh region; key facts specify Riyadh province, Saudi Arabia.
Status: reported
Attribution: acwapower.com
Source: acwapower.com — https://acwapower.com/en/what-we-do/projects/rumah-1-ipp/ | published unknown | observed 2026-10-18T07:27:11.032713+00:00

## Developer
ACWA Power.
Status: reported
Attribution: acwapower.com
Source: acwapower.com — https://acwapower.com/en/what-we-do/projects/rumah-1-ipp/ | published unknown | observed 2026-10-18T07:27:11.032713+00:00


## Cite this dossier

CapexCue — Rumah 1 IPP; also described as the “Rumah-1 Independent Power Project.” — dossier released 2026-10-18T07:53:01.450246+00:00, release 1 (e792fbbf-bc47-4487-af76-1d10b31277d6) — https://capexcue.com/projects/rumah-1-ipp-also-described-as-the-rumah-1-independent-power-project-d65a1a35-f17/.

For current information and later dossier updates, visit <https://capexcue.com/projects/rumah-1-ipp-also-described-as-the-rumah-1-independent-power-project-d65a1a35-f17/>.
This file records the release identified above; the current dossier may change.