# Blackstone Battery Energy Storage System (BESS) Project

Publisher: CapexCue
Canonical dossier: <https://capexcue.com/projects/blackstone-battery-energy-storage-system-bess-project-27c2dcae-35f/>
Dossier reference: release 1 (217bcbfc-f792-41ca-a80a-31c19cc3912d)

Released project intelligence

Oldest supporting observation: 2026-10-17T12:07:49.086057+00:00
Dossier released: 2026-10-17T12:27:38.754051+00:00
Source report dates and capture dates are listed per fact below; neither establishes an event date.

Original released project name: Blackstone Battery Energy Storage System (BESS) Project.

## Project summary

The referral describes a proposed 500 MW / 2,000 MWh standalone battery storage project at 45 Patrick Street, Swanbank, Queensland, with an approximately 7.25 ha footprint and associated substation, underground cables, site infrastructure, batching plant and mine-remediation works. Approximately 3.26 ha of mapped koala habitat is within the footprint; 2026 surveys identified habitat resources but directly observed no koalas. 

Construction is expected to run from November 2026 to Q1 2029. The portal displays “Referral Decision Made,” but the captured page is offline/read-only, warns that some status fields may update, and provides no usable details in its related-decisions table. The description lists approvals, financing, EPC/LTSA execution and Powerlink agreements as future steps; it does not document an open procurement opportunity.

## Evidence limits and unknowns

- The portal capture was observed on 2026-10-17; the source provides no publication date. Current project status after that capture is not established.
- The source does not establish whether financing, approvals, agreements or the Q4 2026 milestone have since been completed.
- The project description does not state a budget or financing amount.
- The related-decisions table provides no usable decision details.

Current purchasing availability: unknown.
Source-dated plans do not establish current progress or available supplier packages.

## Project metadata

Country: Australia
Region: Oceania
Physical assets: Battery Storage, Electricity Transmission
Derived from the exact released evidence; unresolved fields remain unclassified.

## Project category

Energy
Derived from the reviewed scope statement; delivery stage remains unclassified.
Proposed 500 MW / 2,000 MWh standalone battery energy storage facility, with an approximately 7.25 ha project and disturbance footprint. Associated planned works include a new 275 kV substation, 275 kV underground cables to the existing Blackstone Substation, access roads, stormwater infrastructure, an operations and maintenance building, battery and electrical equipment, a temporary concrete batching plant, and mine remediation associated with historical underground tunnels in the eastern portion of the site.
Source: epbcpublicportal.environment.gov.au — https://epbcpublicportal.environment.gov.au/all-referrals/project-referral-summary/?id=b82ae61b-219d-f111-b8db-6045bde6a109 | published unknown | observed 2026-10-17T12:07:49.086057+00:00

Project overview
Oldest decisive evidence: 2026-10-17T12:07:49.086057+00:00
Newest evidence: 2026-10-17T12:07:49.086057+00:00
Knowledge reviewed: 2026-10-17T12:25:52.686007+00:00
Publication reviewed: 2026-10-17T12:27:16.945233+00:00

## Date
Construction is expected to start in November 2026 and finish in Q1 2029; operation is expected to start in Q1 2029 and continue until Q1 2054 (approximately 25 years); decommissioning is anticipated to commence in Q2 2054.
Status: planned
Attribution: epbcpublicportal.environment.gov.au
Source: epbcpublicportal.environment.gov.au — https://epbcpublicportal.environment.gov.au/all-referrals/project-referral-summary/?id=b82ae61b-219d-f111-b8db-6045bde6a109 | published unknown | observed 2026-10-17T12:07:49.086057+00:00

## Name
Blackstone Battery Energy Storage System (BESS) Project.
Status: reported
Attribution: epbcpublicportal.environment.gov.au
Source: epbcpublicportal.environment.gov.au — https://epbcpublicportal.environment.gov.au/all-referrals/project-referral-summary/?id=b82ae61b-219d-f111-b8db-6045bde6a109 | published unknown | observed 2026-10-17T12:07:49.086057+00:00

## Scope
Proposed 500 MW / 2,000 MWh standalone battery energy storage facility, with an approximately 7.25 ha project and disturbance footprint. Associated planned works include a new 275 kV substation, 275 kV underground cables to the existing Blackstone Substation, access roads, stormwater infrastructure, an operations and maintenance building, battery and electrical equipment, a temporary concrete batching plant, and mine remediation associated with historical underground tunnels in the eastern portion of the site.
Status: planned
Attribution: epbcpublicportal.environment.gov.au
Source: epbcpublicportal.environment.gov.au — https://epbcpublicportal.environment.gov.au/all-referrals/project-referral-summary/?id=b82ae61b-219d-f111-b8db-6045bde6a109 | published unknown | observed 2026-10-17T12:07:49.086057+00:00

## Ecology
Approximately 3.26 ha of mapped koala habitat is within the project footprint. Field surveys completed in 2026 identified koala habitat resources, but no koalas were directly observed.
Status: reported
Attribution: epbcpublicportal.environment.gov.au
Source: epbcpublicportal.environment.gov.au — https://epbcpublicportal.environment.gov.au/all-referrals/project-referral-summary/?id=b82ae61b-219d-f111-b8db-6045bde6a109 | published unknown | observed 2026-10-17T12:07:49.086057+00:00

## Location
45 Patrick Street, Swanbank, Queensland, in the Swanbank–New Chum industrial precinct, adjacent to the existing Blackstone 275 kV Substation.
Status: reported
Attribution: epbcpublicportal.environment.gov.au
Source: epbcpublicportal.environment.gov.au — https://epbcpublicportal.environment.gov.au/all-referrals/project-referral-summary/?id=b82ae61b-219d-f111-b8db-6045bde6a109 | published unknown | observed 2026-10-17T12:07:49.086057+00:00

## Contractor
Tesla is identified as the planned counterparty for the EPC and LTSA; execution is listed as a future step.
Status: planned
Attribution: epbcpublicportal.environment.gov.au
Source: epbcpublicportal.environment.gov.au — https://epbcpublicportal.environment.gov.au/all-referrals/project-referral-summary/?id=b82ae61b-219d-f111-b8db-6045bde6a109 | published unknown | observed 2026-10-17T12:07:49.086057+00:00

## Regulatory
The portal displays project status “Referral Decision Made,” while the project description lists finalising Operational Works approvals with Ipswich City Council as a future step; neither establishes that all approvals are complete. The captured page states it is an offline, read-only version and warns that project status fields for some projects may update. The related-decisions table shows loading, permission and error messages and provides no usable decision details.
Status: reported
Attribution: epbcpublicportal.environment.gov.au
Source: epbcpublicportal.environment.gov.au — https://epbcpublicportal.environment.gov.au/all-referrals/project-referral-summary/?id=b82ae61b-219d-f111-b8db-6045bde6a109 | published unknown | observed 2026-10-17T12:07:49.086057+00:00

## Procurement
Execution of the EPC and Long-Term Service Agreement (LTSA), and execution of connection and access agreements with Powerlink Queensland for the Blackstone Substation extension and high-voltage underground cables, are listed as future steps. The description does not state that these agreements have been executed.
Status: planned
Attribution: epbcpublicportal.environment.gov.au
Source: epbcpublicportal.environment.gov.au — https://epbcpublicportal.environment.gov.au/all-referrals/project-referral-summary/?id=b82ae61b-219d-f111-b8db-6045bde6a109 | published unknown | observed 2026-10-17T12:07:49.086057+00:00

## Next Milestone
The project description targets financial close and issuance of the Notice to Proceed for construction in Q4 2026.
Status: planned
Attribution: epbcpublicportal.environment.gov.au
Source: epbcpublicportal.environment.gov.au — https://epbcpublicportal.environment.gov.au/all-referrals/project-referral-summary/?id=b82ae61b-219d-f111-b8db-6045bde6a109 | published unknown | observed 2026-10-17T12:07:49.086057+00:00

## Financing Stage
Completing project financing and achieving financial close are listed as steps to be completed following the EPBC Act referral.
Status: planned
Attribution: epbcpublicportal.environment.gov.au
Source: epbcpublicportal.environment.gov.au — https://epbcpublicportal.environment.gov.au/all-referrals/project-referral-summary/?id=b82ae61b-219d-f111-b8db-6045bde6a109 | published unknown | observed 2026-10-17T12:07:49.086057+00:00


## Cite this dossier

CapexCue — Blackstone Battery Energy Storage System (BESS) Project — dossier released 2026-10-17T12:27:38.754051+00:00, release 1 (217bcbfc-f792-41ca-a80a-31c19cc3912d) — https://capexcue.com/projects/blackstone-battery-energy-storage-system-bess-project-27c2dcae-35f/.

For current information and later dossier updates, visit <https://capexcue.com/projects/blackstone-battery-energy-storage-system-bess-project-27c2dcae-35f/>.
This file records the release identified above; the current dossier may change.