Project scope

Plan: The modified scheme is described as covering 363 ha, down from the initial 509 ha project. It includes a 3.7 km motor circuit; a 1,199 m by 23 m airstrip using existing taxiway 2 (about 2.8 ha including clearances); an activity area with about 4,700 m² of existing buildings to be reconfigured for vehicle maintenance and other businesses; four underground fuel tanks with 230 m³ total capacity; three car parks of 990 m², 14,890 m² and 15,625 m²; and a heliport. Other planned facilities include a 31 m² entrance lodge, an 800 m² reception and exhibition space, a 1,500 m² paddock, and 550 m² for offices, race control and medical facilities. Fourteen buildings are to be demolished and another partly demolished, retaining an electrical transformer post. The revised drainage plan reduces seven infiltration basins to five and increases their stated useful volume from 13,781 m³ to 16,853 m³. The opinion reports 67 ha for the autodrome and associated buildings and 194 ha allocated to the separate Neoen project, but says the use of the former base’s remaining land needs clarification; the complete site boundary and land-use split are therefore not reconciled.

Reported status and procurement

Reported development

The 2018 version was not carried out and its development permits expired. MSV subsequently modified the project and is seeking a new development permit. The reviewed pages do not establish that construction has begun or provide an implementation schedule; the authority asks for the works and timetable to be described.

Procurement availability
Unknown / not established

A source report alone does not establish current progress or an open buying window.

Project summary

Autodrome de Laon-Couvron

The environmental opinion dated 10 September 2026 describes a modified motorsport, airfield and activity-area project on the former military air base near Laon, across four communes in Aisne, France. The planned scheme includes a 3.7 km circuit and a 1,199 m airstrip, alongside activity and support facilities.

The opinion says the 2018 version was not carried out and its permits expired. At the time described, MSV was seeking a new development permit; the reviewed pages do not establish a construction start or works timetable.

The five planned infiltration basins are part of the autodrome project but serve rainwater management across the former base, including the separate solar project. The authority asks that the sizing assumptions be justified or reconsidered, including runoff from photovoltaic areas and expected climate changes.

The opinion also identifies unresolved environmental matters, including ecological compensation, groundwater and potable-water compliance, soil information, external traffic effects and greenhouse-gas emissions.

Evidence limits and unknowns

The reviewed opinion does not report the outcome of the modified development-permit process, a construction start or a works timetable; it calls for the works and schedule to be described.

The complete division of the former base among the autodrome, the separate solar project and other uses is not reconciled.

The authority says the compensation assessment does not demonstrate no net biodiversity loss, including when the autodrome and solar project are considered together.

The material reviewed is extracted text from pages 3–15 of the 15-page opinion. Pages 1–2 and graphical content were not interpreted, and OCR was not commissioned.

Is this project a fit for your company?

Check how this project relates to what your company supplies, with evidence gaps and a next step.

Create your account for free and include your business details to get custom commercial assessments.

Project metadata

Country
France
Based on reviewed release evidence
Region
Europe
Physical assets
Not classified

Based on this release's supporting evidence. Unresolved fields remain unclassified; these labels do not establish current progress or a buying window.

Released facts and supporting evidence

Each fact retains its source, uncertainty and time context. If a publisher page moves or is unavailable, use the recorded quotation and observation date below.

Project name

Source reported

Autodrome de Laon-Couvron (modified project).

Attributed to IGEDD / Autorité environnementale.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-05

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-05

IGEDD environmental authority native opinion text
Attributed to IGEDD / Autorité environnementale

Technical record · Autodrome de Laon-Couvron (modified project).
Evidence location
page:3
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
61575f87-5d17-40c4-bf94-37554d8db5ae
Evidence reference
9a825f51-d578-4a41-8fc3-075bcf17a0d2
Source revision
a2d268d4-4fb7-4040-a85b-8128399f4206
Content fingerprint
069af668ffe636521bc9fd22a984bd2f2ec1a3023824895ce977d8ac75528174
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/autodrome_de_laon-couvron_a_chery-les-pouilly_couvron-et-aumencourt_crepy_et_vivaise_02_-_2e_avis_cle2141b4.pdf

Scope

Planned

The modified scheme is described as covering 363 ha, down from the initial 509 ha project. It includes a 3.7 km motor circuit; a 1,199 m by 23 m airstrip using existing taxiway 2 (about 2.8 ha including clearances); an activity area with about 4,700 m² of existing buildings to be reconfigured for vehicle maintenance and other businesses; four underground fuel tanks with 230 m³ total capacity; three car parks of 990 m², 14,890 m² and 15,625 m²; and a heliport. Other planned facilities include a 31 m² entrance lodge, an 800 m² reception and exhibition space, a 1,500 m² paddock, and 550 m² for offices, race control and medical facilities. Fourteen buildings are to be demolished and another partly demolished, retaining an electrical transformer post. The revised drainage plan reduces seven infiltration basins to five and increases their stated useful volume from 13,781 m³ to 16,853 m³. The opinion reports 67 ha for the autodrome and associated buildings and 194 ha allocated to the separate Neoen project, but says the use of the former base’s remaining land needs clarification; the complete site boundary and land-use split are therefore not reconciled.

Attributed to IGEDD / Autorité environnementale.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-05

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-05

IGEDD environmental authority native opinion text
Attributed to IGEDD / Autorité environnementale

Technical record · The modified scheme is described as covering 363 …
Evidence location
page:4
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
f77335c5-b166-4a0c-bcd5-f1ee7f702f4e
Evidence reference
53d16d4a-053b-4f52-8088-786c7b243319
Source revision
a2d268d4-4fb7-4040-a85b-8128399f4206
Content fingerprint
069af668ffe636521bc9fd22a984bd2f2ec1a3023824895ce977d8ac75528174
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/autodrome_de_laon-couvron_a_chery-les-pouilly_couvron-et-aumencourt_crepy_et_vivaise_02_-_2e_avis_cle2141b4.pdf

Country

Source reported

France.

Attributed to IGEDD / Autorité environnementale.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-05

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-05

IGEDD environmental authority native opinion text
Attributed to IGEDD / Autorité environnementale

Technical record · France.
Evidence location
page:3
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
ff415fe4-ec58-45d7-bb99-555fe7428cbf
Evidence reference
9a825f51-d578-4a41-8fc3-075bcf17a0d2
Source revision
a2d268d4-4fb7-4040-a85b-8128399f4206
Content fingerprint
069af668ffe636521bc9fd22a984bd2f2ec1a3023824895ce977d8ac75528174
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/autodrome_de_laon-couvron_a_chery-les-pouilly_couvron-et-aumencourt_crepy_et_vivaise_02_-_2e_avis_cle2141b4.pdf

Project ecology

Source reported

The authority identifies protected species and habitats, biodiversity and ecological continuity, groundwater, contaminated soils and pyrotechnic risks, air quality, noise, traffic and greenhouse-gas emissions as material issues. The 2018 nature-protection opinion was unfavorable. Ecological compensation required under the 2019 authorization covered 242 ha, was only partly implemented, and was interrupted in 2020; at Sissonne, 67 of 132 planned hectares had been completed. The revised assessment estimates 26.68 ha of habitat loss for the Eurasian stone-curlew and 53.36 ha of compensation, but the authority says the overall compensation assessment remains incomplete and does not demonstrate no net biodiversity loss, including cumulatively with the solar project. MSV is reported as proposing no additional compensation. The authority also reports that 2025 analyses found water from the site’s F2 borehole had parameters non-compliant with potable use, and asks for the abstraction level and measures to ensure potable-water compliance to be addressed. Soil contamination and earthworks information remain incomplete. Operating emissions are estimated at about 3,150 tCO2e per year; construction emissions were not estimated, and the claimed carbon compensation is not substantiated. Traffic effects outside the site also remain insufficiently clarified.

Attributed to IGEDD / Autorité environnementale.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-05

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-05

IGEDD environmental authority native opinion text
Attributed to IGEDD / Autorité environnementale

Technical record · The authority identifies protected species and habitats, biodiversity …
Evidence location
page:3
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
c683929b-06ae-40aa-91be-1c85a139e6ac
Evidence reference
9a825f51-d578-4a41-8fc3-075bcf17a0d2
Source revision
a2d268d4-4fb7-4040-a85b-8128399f4206
Content fingerprint
069af668ffe636521bc9fd22a984bd2f2ec1a3023824895ce977d8ac75528174
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/autodrome_de_laon-couvron_a_chery-les-pouilly_couvron-et-aumencourt_crepy_et_vivaise_02_-_2e_avis_cle2141b4.pdf

Current activity

Planned

Planned uses include sports-car and motorcycle owner driving days, manufacturer events and tests, driving courses, up to six car or motorcycle race weekends per year, driver and road-safety training, and training for emergency services. Leisure and sports operation is planned for daytime hours, with specified weekday and weekend limits; industrial testing is envisaged around the clock. Airfield use is limited to daylight and specified operating hours, with the dossier estimating up to 10 aircraft movements per day.

Attributed to IGEDD / Autorité environnementale.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-05

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-05

IGEDD environmental authority native opinion text
Attributed to IGEDD / Autorité environnementale

Technical record · Planned uses include sports-car and motorcycle owner driving …
Evidence location
page:6
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
582835ae-acd5-4bae-a2b0-d012e2fd7eec
Evidence reference
19776d8b-324d-422a-8511-22045f016c2b
Source revision
a2d268d4-4fb7-4040-a85b-8128399f4206
Content fingerprint
069af668ffe636521bc9fd22a984bd2f2ec1a3023824895ce977d8ac75528174
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/autodrome_de_laon-couvron_a_chery-les-pouilly_couvron-et-aumencourt_crepy_et_vivaise_02_-_2e_avis_cle2141b4.pdf

Delivery

Source reported

The 2018 version was not carried out and its development permits expired. MSV subsequently modified the project and is seeking a new development permit. The reviewed pages do not establish that construction has begun or provide an implementation schedule; the authority asks for the works and timetable to be described.

Attributed to IGEDD / Autorité environnementale.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-05

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-05

IGEDD environmental authority native opinion text
Attributed to IGEDD / Autorité environnementale

Technical record · The 2018 version was not carried out and …
Evidence location
page:4
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
1e232840-bebf-4c60-91c1-34f42e602183
Evidence reference
53d16d4a-053b-4f52-8088-786c7b243319
Source revision
a2d268d4-4fb7-4040-a85b-8128399f4206
Content fingerprint
069af668ffe636521bc9fd22a984bd2f2ec1a3023824895ce977d8ac75528174
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/autodrome_de_laon-couvron_a_chery-les-pouilly_couvron-et-aumencourt_crepy_et_vivaise_02_-_2e_avis_cle2141b4.pdf

Location

Source reported

On the former NATO military air base near Laon, across Chéry-lès-Pouilly, Couvron-et-Aumencourt, Vivaise and Crépy, in the Aisne department (02). The former base is described as 509 ha, with existing buildings, roads and a 94 ha airfield; it has not been used since 2012.

Attributed to IGEDD / Autorité environnementale.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-05

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-05

IGEDD environmental authority native opinion text
Attributed to IGEDD / Autorité environnementale

Technical record · On the former NATO military air base near …
Evidence location
page:3
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
f291c7df-8bc4-49bf-a6b5-d324f032a48e
Evidence reference
9a825f51-d578-4a41-8fc3-075bcf17a0d2
Source revision
a2d268d4-4fb7-4040-a85b-8128399f4206
Content fingerprint
069af668ffe636521bc9fd22a984bd2f2ec1a3023824895ce977d8ac75528174
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/autodrome_de_laon-couvron_a_chery-les-pouilly_couvron-et-aumencourt_crepy_et_vivaise_02_-_2e_avis_cle2141b4.pdf

Next milestone

Unknown

The new development-permit dossier is under examination in the reviewed account. Its decision and any subsequent construction milestone are not reported; a works schedule remains to be clarified.

Attributed to IGEDD / Autorité environnementale.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-05

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-05

IGEDD environmental authority native opinion text
Attributed to IGEDD / Autorité environnementale

Technical record · The new development-permit dossier is under examination in …
Evidence location
page:8
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
38c2f96b-15d3-4a6f-8c1d-d853c7b98928
Evidence reference
f11f10a9-379e-4a68-855c-4f0bffbd48f8
Source revision
a2d268d4-4fb7-4040-a85b-8128399f4206
Content fingerprint
069af668ffe636521bc9fd22a984bd2f2ec1a3023824895ce977d8ac75528174
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/autodrome_de_laon-couvron_a_chery-les-pouilly_couvron-et-aumencourt_crepy_et_vivaise_02_-_2e_avis_cle2141b4.pdf
Source report history

Prior and superseded states remain labelled. Dates below identify source publication when known, otherwise source observation. They are not assumed event dates; each fact retains its own time qualifications.

  1. No material timeline events have been released.

Follow this project

Get project updates by email when new information is published.

Follow for free without an account, with the option to unsubscribe anytime. We'll email you a link to confirm.

DEEPRFP, S.L.U. uses your email and selected project to confirm and deliver the updates you request. You can stop anytime. Product news needs a separate opt-in. Read the Privacy Policy for legal bases, recipients, retention, your rights and contact details.