Cachuma Project

United States · Water and environment

In-depth research Release 1

Project scope

An integrated system comprising Bradbury Dam and Lake Cachuma; the 6.4-mile Tecolote Tunnel; the 24-mile South Coast Conduit and four regulating reservoirs; and localized distribution systems with lateral pipelines and pumping plants. The Carpinteria system also includes an elevated 50,000-gallon tank. The page gives Bradbury Dam as 279 feet high from the bottom of the cutoff trench to the top, and Lake Cachuma as having a capacity of 193,300 acre-feet and a 42-mile shoreline.

Reported status and procurement

Reported development

Stores Santa Ynez River floodwaters and conveys water from Lake Cachuma through the Tecolote Tunnel and South Coast Conduit to South Coast water districts, agricultural lands and municipal users, including Santa Barbara.

Procurement availability
Unknown / not established

A source report alone does not establish current progress or an open buying window.

Project summary

The Bureau of Reclamation page identifies the Cachuma Project in California. It describes Bradbury Dam on the Santa Ynez River, about 25 miles northwest of Santa Barbara, storing river floodwaters that are conveyed through the Tecolote Tunnel and South Coast Conduit to South Coast agricultural and municipal users, including Santa Barbara. The page describes a 6.4-mile tunnel, a 24-mile conduit and four regulating reservoirs. It also reports that Glen Anne Reservoir was permanently restricted on August 19, 2002, because of seismic-related risks, and is maintained but no longer operated. The page reports estimated annual evaporation losses of 16,000 acre-feet and describes sediment buildup despite mitigation efforts.

Evidence limits and unknowns

The supplied page context gives no publication or as-of date. In particular, it does not date its present-tense description of Glen Anne Reservoir’s status.

The supplied page does not identify a current project package, budget or financing, procurement status, current capital works, or next milestone; its Plan and Other sections contain no text.

The supplied evidence covers the page’s visible text, not the linked Cachuma Project History document, which was not acquired or interpreted.

Is this project a fit for your company?

Check how this project relates to what your company supplies, with evidence gaps and a next step.

Create your account for free and include your business details to get custom commercial assessments.

Project metadata

Country
United States
Based on reviewed release evidence
Region
North America
Category
Water and environment
Derived from released evidence
Physical assets
Not classified

Based on this release's supporting evidence. Unresolved fields remain unclassified; these labels do not establish current progress or a buying window.

Released facts and supporting evidence

Each fact retains its source, uncertainty and time context. If a publisher page moves or is unavailable, use the recorded quotation and observation date below.

Project name

Source reported

Cachuma Project

Attributed to USBR official owntext and attributed factual synthesis.

Source: US Bureau of Reclamation screened government project narrative · publication date not recorded · observed 2026-10-03

Sources and evidence · US Bureau of Reclamation screened government project narrative
Source published: Not recordedObserved: 2026-10-03

US Bureau of Reclamation screened government project narrative
Attributed to USBR official owntext and attributed factual synthesis

Technical record · Cachuma Project
Evidence location
/html/body/div/div[4]/div/div[2]/div[3]/div[1]/h1
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
b4a80b90-5f09-4db3-9f10-3d380d9348df
Evidence reference
2897859b-b278-4a29-a299-217f4f033255
Source revision
9aada6f2-e517-451d-9a3c-acb33d243dec
Content fingerprint
fd0dfd34f8817a4acf3a32fba5f0f2d70b68bff7021634aa7f482e7aa949b990
Source address
https://www.usbr.gov/projects/index.php?id=336

Scope

Source reported

An integrated system comprising Bradbury Dam and Lake Cachuma; the 6.4-mile Tecolote Tunnel; the 24-mile South Coast Conduit and four regulating reservoirs; and localized distribution systems with lateral pipelines and pumping plants. The Carpinteria system also includes an elevated 50,000-gallon tank. The page gives Bradbury Dam as 279 feet high from the bottom of the cutoff trench to the top, and Lake Cachuma as having a capacity of 193,300 acre-feet and a 42-mile shoreline.

Attributed to USBR official owntext and attributed factual synthesis.

Source: US Bureau of Reclamation screened government project narrative · publication date not recorded · observed 2026-10-03

Sources and evidence · US Bureau of Reclamation screened government project narrative
Source published: Not recordedObserved: 2026-10-03

US Bureau of Reclamation screened government project narrative
Attributed to USBR official owntext and attributed factual synthesis

Technical record · An integrated system comprising Bradbury Dam and Lake …
Evidence location
/html/body/div/div[4]/div/div[2]/div[3]/div[8]/p[3]
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
50c620d3-a68e-447f-9442-15585f962fea
Evidence reference
dc97c0da-56f8-479c-8528-9102652e03b5
Source revision
9aada6f2-e517-451d-9a3c-acb33d243dec
Content fingerprint
fd0dfd34f8817a4acf3a32fba5f0f2d70b68bff7021634aa7f482e7aa949b990
Source address
https://www.usbr.gov/projects/index.php?id=336

Project ecology

Source reported

The page reports estimated annual evaporation losses of 16,000 acre-feet and describes silt washing into Lake Cachuma from chaparral flora, rainstorms, landslides and wildfires; it says attempted mitigation had made little impact on the buildup.

Attributed to USBR official owntext and attributed factual synthesis.

Source: US Bureau of Reclamation screened government project narrative · publication date not recorded · observed 2026-10-03

Sources and evidence · US Bureau of Reclamation screened government project narrative
Source published: Not recordedObserved: 2026-10-03

US Bureau of Reclamation screened government project narrative
Attributed to USBR official owntext and attributed factual synthesis

Technical record · The page reports estimated annual evaporation losses of …
Evidence location
/html/body/div/div[4]/div/div[2]/div[3]/div[6]/p[3]
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
61344b57-de05-45fb-a47a-f739bea8c6c1
Evidence reference
16a9e6cc-ace3-4aee-a883-5ee7968e0d27
Source revision
9aada6f2-e517-451d-9a3c-acb33d243dec
Content fingerprint
fd0dfd34f8817a4acf3a32fba5f0f2d70b68bff7021634aa7f482e7aa949b990
Source address
https://www.usbr.gov/projects/index.php?id=336

Current activity

Source reported

The page says the project was authorized in 1948, construction began in 1950 and the project was completed in 1956. It separately dates construction of Bradbury Dam and the South Coast Conduit to 1950–1953, the regulating reservoirs to 1951–1954, and distribution systems to 1952–1956, with those systems operable by early 1956. The page also reports that Glen Anne Reservoir was placed under permanent restriction on August 19, 2002, due to seismic-related risks, and says it is maintained but no longer operated.

Attributed to USBR official owntext and attributed factual synthesis.

Source: US Bureau of Reclamation screened government project narrative · publication date not recorded · observed 2026-10-03

Sources and evidence · US Bureau of Reclamation screened government project narrative
Source published: Not recordedObserved: 2026-10-03

US Bureau of Reclamation screened government project narrative
Attributed to USBR official owntext and attributed factual synthesis

Technical record · The page says the project was authorized in …
Evidence location
/html/body/div/div[4]/div/div[2]/div[3]/div[4]/p[2]
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
90b08421-3884-47e8-9d1c-21cd4f426254
Evidence reference
b1eeb602-a5d2-4872-a71c-be0d4f174f7b
Source revision
9aada6f2-e517-451d-9a3c-acb33d243dec
Content fingerprint
fd0dfd34f8817a4acf3a32fba5f0f2d70b68bff7021634aa7f482e7aa949b990
Source address
https://www.usbr.gov/projects/index.php?id=336

Delivery

Source reported

Stores Santa Ynez River floodwaters and conveys water from Lake Cachuma through the Tecolote Tunnel and South Coast Conduit to South Coast water districts, agricultural lands and municipal users, including Santa Barbara.

Attributed to USBR official owntext and attributed factual synthesis.

Source: US Bureau of Reclamation screened government project narrative · publication date not recorded · observed 2026-10-03

Sources and evidence · US Bureau of Reclamation screened government project narrative
Source published: Not recordedObserved: 2026-10-03

US Bureau of Reclamation screened government project narrative
Attributed to USBR official owntext and attributed factual synthesis

Technical record · Stores Santa Ynez River floodwaters and conveys water …
Evidence location
/html/body/div/div[4]/div/div[2]/div[3]/div[8]/p[2]
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
4194685a-eb4b-4840-acd0-60c94244f21f
Evidence reference
ec89c981-12e4-41bb-8a9b-b3289bece902
Source revision
9aada6f2-e517-451d-9a3c-acb33d243dec
Content fingerprint
fd0dfd34f8817a4acf3a32fba5f0f2d70b68bff7021634aa7f482e7aa949b990
Source address
https://www.usbr.gov/projects/index.php?id=336

Location

Source reported

California’s South Coast, with Bradbury Dam on the Santa Ynez River approximately 25 miles northwest of Santa Barbara. The system serves the South Coast area, including Santa Barbara and water districts in Goleta, Montecito, Summerland and Carpinteria.

Attributed to USBR official owntext and attributed factual synthesis.

Source: US Bureau of Reclamation screened government project narrative · publication date not recorded · observed 2026-10-03

Sources and evidence · US Bureau of Reclamation screened government project narrative
Source published: Not recordedObserved: 2026-10-03

US Bureau of Reclamation screened government project narrative
Attributed to USBR official owntext and attributed factual synthesis

Technical record · California’s South Coast, with Bradbury Dam on the …
Evidence location
/html/body/div/div[4]/div/div[2]/div[3]/div[1]/div[2]/p[1]
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
fb17639f-5b0b-4f33-b9be-cc7af6156824
Evidence reference
62cdefc0-3b90-43c0-a564-7dc6a4bae538
Source revision
9aada6f2-e517-451d-9a3c-acb33d243dec
Content fingerprint
fd0dfd34f8817a4acf3a32fba5f0f2d70b68bff7021634aa7f482e7aa949b990
Source address
https://www.usbr.gov/projects/index.php?id=336

Implementing agency

Source reported

The Bureau of Reclamation is reported to have constructed the Goleta, Carpinteria and Summerland distribution systems and to operate Bradbury Dam. The page says each district for which a system was built is responsible for its operation and maintenance, and member units acting through the Cachuma Operation and Maintenance Board operate the rest of the project.

Attributed to USBR official owntext and attributed factual synthesis.

Source: US Bureau of Reclamation screened government project narrative · publication date not recorded · observed 2026-10-03

Sources and evidence · US Bureau of Reclamation screened government project narrative
Source published: Not recordedObserved: 2026-10-03

US Bureau of Reclamation screened government project narrative
Attributed to USBR official owntext and attributed factual synthesis

Technical record · The Bureau of Reclamation is reported to have …
Evidence location
/html/body/div/div[4]/div/div[2]/div[3]/div[6]/p[3]
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
7f63b86c-e96a-4eef-ab8f-e1f8c6b30c39
Evidence reference
5e81862e-b528-417b-b131-a797f620478c
Source revision
9aada6f2-e517-451d-9a3c-acb33d243dec
Content fingerprint
fd0dfd34f8817a4acf3a32fba5f0f2d70b68bff7021634aa7f482e7aa949b990
Source address
https://www.usbr.gov/projects/index.php?id=336
Source report history

Prior and superseded states remain labelled. Dates below identify source publication when known, otherwise source observation. They are not assumed event dates; each fact retains its own time qualifications.

  1. No material timeline events have been released.

Follow this project

Get project updates by email when new information is published.

Follow for free without an account, with the option to unsubscribe anytime. We'll email you a link to confirm.

DEEPRFP, S.L.U. uses your email and selected project to confirm and deliver the updates you request. You can stop anytime. Product news needs a separate opt-in. Read the Privacy Policy for legal bases, recipients, retention, your rights and contact details.