Clements Gap Battery, also referred to as the Clements Gap BESS.
Australia · Energy
In-depth researchRelease 1
Project scope
A 60 MW (120 MWh) battery energy storage system, located beside the wind farm and capitalising on its grid connection. The project description says it will store excess electricity from the grid for use when demand requires it.
Reported status and procurement
Reported development
A September 2025 update reported delivery of all 50 battery modules, 25 inverters, the new project control room and the transformer.
Procurement availability
Unknown / not established
Reported regulatory context
Development Authorisation was granted on 11 May 2021; a variation allowing increased battery capacity was approved on 11 November 2022.
A source report alone does not establish current progress or an open buying window.
Project summary
Clements Gap Battery, also referred to as Clements Gap BESS, is a 60 MW / 120 MWh battery energy storage project beside the Clements Gap Wind Farm in South Australia’s mid-north, about 20 km northeast of Port Broughton. Pacific Blue’s December 2025 update reported first energisation on 9 December 2025, major construction works complete, and the project entering commissioning. That update described staged commissioning and looked toward full operation and completion in 2026; the page timeline lists Q1 2026 for commissioning and commencement of operations as targets, not confirmed achievements.
Evidence limits and unknowns
The supplied page does not confirm that full operations have commenced or that project completion has been achieved. Its December 2025 update describes staged commissioning and prospective 2026 completion; the timeline lists Q1 2026 milestones.
The supplied page material does not identify a current open procurement package or supplier opportunity. Its timeline notes that an EPC contractor was nominated and lists commissioning and operations milestones for Q1 2026.
Is this project a fit for your company?
Check how this project relates to what your company supplies, with evidence gaps and a next step.
Create your account for free and include your business details to get custom commercial assessments.
Project metadata
Country
Australia Based on reviewed release evidence
Region
Oceania
Category
Energy Derived from released evidence
Physical assets
Battery Storage
Based on this release's supporting evidence. Unresolved fields remain unclassified; these labels do not establish current progress or a buying window.
Released facts and supporting evidence
Each fact retains its source, uncertainty and time context. If a publisher page moves or is unavailable, use the recorded quotation and observation date below.
Project name
Source reported
Clements Gap Battery, also referred to as the Clements Gap BESS.
Attributed to www.pacificblue.com.au.
Source: www.pacificblue.com.au · publication date not recorded · observed 2026-10-17
Sources and evidence · www.pacificblue.com.au
Source published: Not recordedObserved: 2026-10-17
A 60 MW (120 MWh) battery energy storage system, located beside the wind farm and capitalising on its grid connection. The project description says it will store excess electricity from the grid for use when demand requires it.
Attributed to www.pacificblue.com.au.
Source: www.pacificblue.com.au · publication date not recorded · observed 2026-10-17
Sources and evidence · www.pacificblue.com.au
Source published: Not recordedObserved: 2026-10-17
Pacific Blue reported first energisation on 9 December 2025, marking the completion of major construction works and transition to commissioning. The update said the system was connected to the grid and able to receive and store electricity.
Attributed to www.pacificblue.com.au.
Source: www.pacificblue.com.au · publication date not recorded · observed 2026-10-17
Sources and evidence · www.pacificblue.com.au
Source published: Not recordedObserved: 2026-10-17
Adjacent to the existing Clements Gap Wind Farm in South Australia’s mid-north, approximately 20 km northeast of Port Broughton and 160 km from Adelaide’s CBD.
Attributed to www.pacificblue.com.au.
Source: www.pacificblue.com.au · publication date not recorded · observed 2026-10-17
Sources and evidence · www.pacificblue.com.au
Source published: Not recordedObserved: 2026-10-17
The December 2025 update said commissioning would take place in stages and looked toward full operation and project completion in 2026. The page timeline separately lists commissioning and commencement of operations for Q1 2026; these are targets, not reported achievements.
Attributed to www.pacificblue.com.au.
Source: www.pacificblue.com.au · publication date not recorded · observed 2026-10-17
Sources and evidence · www.pacificblue.com.au
Source published: Not recordedObserved: 2026-10-17
Prior and superseded states remain labelled. Dates below identify source publication when known, otherwise source observation. They are not assumed event dates; each fact retains its own time qualifications.
No material timeline events have been released.
Follow this project
Get project updates by email when new information is published.
Follow for free without an account, with the option to unsubscribe anytime. We'll email you a link to confirm.
DEEPRFP, S.L.U. uses your email and selected project to confirm and deliver the updates you request. You can stop anytime. Product news needs a separate opt-in. Read the Privacy Policy for legal bases, recipients, retention, your rights and contact details.