Contournement Ouest de Montpellier (COM) (34).

France · Transport and logistics

In-depth research Release 1

Project scope

Plan: The stated aim is to connect the A750 via the RN109 to the A709 and provide exchanges with the RM5 and RM613. The project upgrades three existing metropolitan-road sections in place over about 6 km to two lanes in each direction; part of the route, 1,700 m, is already in that configuration. The works include interchanges and changes to existing junctions or roundabouts, hydraulic works, water collection and treatment, acoustic barriers and earth berms, landscaping, and restored circulation routes. Transport-reserved lanes were extended across the COM perimeter, with exclusions at the Rieu Coulon interchange ramps and ramps to or from the A709. At the Mosson, the design changed from an earlier 47 m structure with an embankment to a 280 m viaduct intended to cross the watercourse and its flood zone with less embankment. The source gives a 90 km/h speed limit and reports that the planned speed on the southern section is higher than the commitments associated with the public-utility declaration. The project also involves excavation and embankment works, including in a flood zone; the dossier says some excavated material will be reused and some material brought in from outside.

Reported status and procurement

Reported development

The project was initially carried by the State through DREAL Occitanie for works on the non-conceded national road network. The source says ASF (Société des autoroutes du sud de la France, Vinci Autoroutes group) is now the project owner through extension of its concession network, and that the State entrusted the project concession to ASF. These are project-owner and concession roles; the supplied pages do not identify a construction contractor.

Procurement availability
Unknown / not established

Reported regulatory context

The project was declared of public utility by ministerial order of 2 September 2021, amended on 14 October 2024. The dossier is presented to obtain authorizations required for the works, including environmental authorization, forest-clearing authorization, authorization for felling aligned trees and a protected-species derogation. The referral dossier was received on 21 November 2024. The opinion procedure was suspended from 13 January 2025, when additional information was requested, until the petitioner responded on 18 March 2025. The second opinion was adopted on 15 May 2025. It is an advisory opinion, neither favorable nor unfavorable, and is not the authorization decision; the supplied pages do not establish the outcome of the authorization applications.

A source report alone does not establish current progress or an open buying window.

Project summary

The 15 May 2025 second opinion describes the Contournement Ouest de Montpellier (COM) as a planned, approximately 6 km upgrade of existing roads west of Montpellier, connecting the A750 via the RN109 to the A709. Three metropolitan-road sections are to be brought to two lanes in each direction; 1,700 m was already in that configuration.

The planned works also include junction and interchange changes, water-management infrastructure, acoustic barriers and berms, landscaping, and circulation reinstatement. At the Mosson, the design was changed to a 280 m viaduct instead of an earlier shorter structure with an embankment.

The opinion identifies ASF (Vinci Autoroutes group) as project owner and describes the expressway as free to use. Its schedule—works and improvements during 2025–2030, main works envisaged from September 2026 and commissioning envisaged in September 2030—was a forecast, not confirmation of delivery.

The authority says important aspects of the traffic analysis were not updated and recommends updating related assessments, including air quality, noise and greenhouse-gas emissions, as well as reworking the socio-economic study. Its opinion is advisory, not an authorization decision.

Evidence limits and unknowns

The reviewed pages do not establish whether the required environmental, forest-clearing, aligned-tree or protected-species authorizations were granted, refused or remain under consideration. The opinion is advisory, not the authorization decision.

Actual construction start, progress, commissioning and current project cost are not established. The schedule was forecast in May 2025; the opinion also says the reported project cost had not been updated for the authorization dossier.

The reviewed pages identify ASF as project owner but do not establish a construction award, supplier package, procurement outcome or current purchasing opportunity.

The available extract covers pages 1–12, 38, 40 and 41 of the 41-page opinion. Pages 13–37 and 39 and graphical content were not reviewed.

Is this project a fit for your company?

Check how this project relates to what your company supplies, with evidence gaps and a next step.

Create your account for free and include your business details to get custom commercial assessments.

Project metadata

Country
France
Based on reviewed release evidence
Region
Europe
Category
Transport and logistics
Derived from released evidence
Physical assets
Road

Based on this release's supporting evidence. Unresolved fields remain unclassified; these labels do not establish current progress or a buying window.

Released facts and supporting evidence

Each fact retains its source, uncertainty and time context. If a publisher page moves or is unavailable, use the recorded quotation and observation date below.

Project name

Source reported

Contournement Ouest de Montpellier (COM) (34).

Attributed to IGEDD Autorité environnementale opinion: authority synthesis and attributed developer facts.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-02

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-02

IGEDD environmental authority native opinion text
Attributed to IGEDD Autorité environnementale opinion: authority synthesis and attributed developer facts

Technical record · Contournement Ouest de Montpellier (COM) (34).
Evidence location
page:1
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
ac90dba1-c456-4c58-acbc-222577741667
Evidence reference
81cd0841-8fc2-46c7-9326-25b651e669e7
Source revision
2eecfaa2-8255-4cdd-bd8d-775785a78971
Content fingerprint
0ef8c70decfaf1c3db84e18d8d53be98a488d6bc88568d0d35ee362c64fff970
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/contournement_ouest_de_montpellier_com_-_2e_avis_cle5f7c8f.pdf

Scope

Planned

The stated aim is to connect the A750 via the RN109 to the A709 and provide exchanges with the RM5 and RM613. The project upgrades three existing metropolitan-road sections in place over about 6 km to two lanes in each direction; part of the route, 1,700 m, is already in that configuration. The works include interchanges and changes to existing junctions or roundabouts, hydraulic works, water collection and treatment, acoustic barriers and earth berms, landscaping, and restored circulation routes. Transport-reserved lanes were extended across the COM perimeter, with exclusions at the Rieu Coulon interchange ramps and ramps to or from the A709. At the Mosson, the design changed from an earlier 47 m structure with an embankment to a 280 m viaduct intended to cross the watercourse and its flood zone with less embankment. The source gives a 90 km/h speed limit and reports that the planned speed on the southern section is higher than the commitments associated with the public-utility declaration. The project also involves excavation and embankment works, including in a flood zone; the dossier says some excavated material will be reused and some material brought in from outside.

Attributed to IGEDD Autorité environnementale opinion: authority synthesis and attributed developer facts.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-02

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-02

IGEDD environmental authority native opinion text
Attributed to IGEDD Autorité environnementale opinion: authority synthesis and attributed developer facts

Technical record · The stated aim is to connect the A750 …
Evidence location
page:8
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
9d7fc5f4-b95a-4838-a568-c2d832030413
Evidence reference
5e87ae67-70e7-4add-a4b5-c076109d6efc
Source revision
2eecfaa2-8255-4cdd-bd8d-775785a78971
Content fingerprint
0ef8c70decfaf1c3db84e18d8d53be98a488d6bc88568d0d35ee362c64fff970
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/contournement_ouest_de_montpellier_com_-_2e_avis_cle5f7c8f.pdf

Current activity

Planned

Improvement of existing road axes to form a free-to-use expressway connection; the source describes an intended connection and improved exchanges between the named routes, not a road built solely on a new alignment.

Attributed to IGEDD Autorité environnementale opinion: authority synthesis and attributed developer facts.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-02

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-02

IGEDD environmental authority native opinion text
Attributed to IGEDD Autorité environnementale opinion: authority synthesis and attributed developer facts

Technical record · Improvement of existing road axes to form a …
Evidence location
page:3
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
eb8c5f16-b99d-4e45-af7c-ade7998e7b49
Evidence reference
4ce61555-e32f-4560-9a6f-eca9708f9f06
Source revision
2eecfaa2-8255-4cdd-bd8d-775785a78971
Content fingerprint
0ef8c70decfaf1c3db84e18d8d53be98a488d6bc88568d0d35ee362c64fff970
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/contournement_ouest_de_montpellier_com_-_2e_avis_cle5f7c8f.pdf

Delivery

Source reported

The project was initially carried by the State through DREAL Occitanie for works on the non-conceded national road network. The source says ASF (Société des autoroutes du sud de la France, Vinci Autoroutes group) is now the project owner through extension of its concession network, and that the State entrusted the project concession to ASF. These are project-owner and concession roles; the supplied pages do not identify a construction contractor.

Attributed to IGEDD Autorité environnementale opinion: authority synthesis and attributed developer facts.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-02

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-02

IGEDD environmental authority native opinion text
Attributed to IGEDD Autorité environnementale opinion: authority synthesis and attributed developer facts

Technical record · The project was initially carried by the State …
Evidence location
page:7
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
938d0468-9f6b-4c56-99b8-5b76140042bd
Evidence reference
64654ae6-a352-411c-90a6-235b8b9b9633
Source revision
2eecfaa2-8255-4cdd-bd8d-775785a78971
Content fingerprint
0ef8c70decfaf1c3db84e18d8d53be98a488d6bc88568d0d35ee362c64fff970
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/contournement_ouest_de_montpellier_com_-_2e_avis_cle5f7c8f.pdf

Location

Source reported

West of Montpellier, in Hérault (34). The public-utility declaration covered Juvignac, Saint-Jean-de-Védas and Montpellier.

Attributed to IGEDD Autorité environnementale opinion: authority synthesis and attributed developer facts.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-02

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-02

IGEDD environmental authority native opinion text
Attributed to IGEDD Autorité environnementale opinion: authority synthesis and attributed developer facts

Technical record · West of Montpellier, in Hérault (34). The public-utility …
Evidence location
page:6
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
f6ca45fa-9e19-4618-ab2e-8072cffb742e
Evidence reference
68e15e01-0f59-434b-b787-a451e5eb676c
Source revision
2eecfaa2-8255-4cdd-bd8d-775785a78971
Content fingerprint
0ef8c70decfaf1c3db84e18d8d53be98a488d6bc88568d0d35ee362c64fff970
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/contournement_ouest_de_montpellier_com_-_2e_avis_cle5f7c8f.pdf

Regulatory evidence

Source reported

The project was declared of public utility by ministerial order of 2 September 2021, amended on 14 October 2024. The dossier is presented to obtain authorizations required for the works, including environmental authorization, forest-clearing authorization, authorization for felling aligned trees and a protected-species derogation. The referral dossier was received on 21 November 2024. The opinion procedure was suspended from 13 January 2025, when additional information was requested, until the petitioner responded on 18 March 2025. The second opinion was adopted on 15 May 2025. It is an advisory opinion, neither favorable nor unfavorable, and is not the authorization decision; the supplied pages do not establish the outcome of the authorization applications.

Attributed to IGEDD Autorité environnementale opinion: authority synthesis and attributed developer facts.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-02

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-02

IGEDD environmental authority native opinion text
Attributed to IGEDD Autorité environnementale opinion: authority synthesis and attributed developer facts

Technical record · The project was declared of public utility by …
Evidence location
page:7
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
af5d03fd-8586-424e-8ab0-86df20b6e908
Evidence reference
329f8816-d919-47e7-8762-a45a3a8c6194
Source revision
2eecfaa2-8255-4cdd-bd8d-775785a78971
Content fingerprint
0ef8c70decfaf1c3db84e18d8d53be98a488d6bc88568d0d35ee362c64fff970
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/contournement_ouest_de_montpellier_com_-_2e_avis_cle5f7c8f.pdf

Next milestone

Planned

The May 2025 opinion forecast works and improvements during 2025–2030, with main works envisaged to start in September 2026 and commissioning envisaged in September 2030. These are forecasts, not evidence that the dates were subsequently met.

Attributed to IGEDD Autorité environnementale opinion: authority synthesis and attributed developer facts.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-02

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-02

IGEDD environmental authority native opinion text
Attributed to IGEDD Autorité environnementale opinion: authority synthesis and attributed developer facts

Technical record · The May 2025 opinion forecast works and improvements …
Evidence location
page:8
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
9c6c70b1-aeac-4286-b731-b999205c7edc
Evidence reference
25a8659b-fae9-4776-b5c8-da87b369800f
Source revision
2eecfaa2-8255-4cdd-bd8d-775785a78971
Content fingerprint
0ef8c70decfaf1c3db84e18d8d53be98a488d6bc88568d0d35ee362c64fff970
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/contournement_ouest_de_montpellier_com_-_2e_avis_cle5f7c8f.pdf
Source report history

Prior and superseded states remain labelled. Dates below identify source publication when known, otherwise source observation. They are not assumed event dates; each fact retains its own time qualifications.

  1. No material timeline events have been released.

Follow this project

Get project updates by email when new information is published.

Follow for free without an account, with the option to unsubscribe anytime. We'll email you a link to confirm.

DEEPRFP, S.L.U. uses your email and selected project to confirm and deliver the updates you request. You can stop anytime. Product news needs a separate opt-in. Read the Privacy Policy for legal bases, recipients, retention, your rights and contact details.