Skip to content
Menu
CapexCue · Public evidence · Printed 11 Nov 2026
Explore projects / Project dossier

Purulia Pumped Storage Project (PPSP)

India · Energy

In-depth research Release 1

Project scope

A closed-loop pumped-storage plant with 900 MW installed capacity (4 × 225 MW). The physical works include upper and lower rockfill dams and reservoirs, twin water conductors, an underground powerhouse with four reversible vertical Francis pump-turbines, an underground transformer cavern with four main transformers, an access tunnel, a 400 kV gas-insulated switchyard, a cable tunnel, and two 400 kV double-circuit transmission lines connected with Durgapur and New PPSP substations.

Reported status and procurement

Reported development

The page states that PPSP units operate in generation, pumping, and synchronous-condenser modes.

Procurement availability
Unknown / not established

A source report alone does not establish current progress or an open buying window.

Project summary

Purulia Pumped Storage Project (PPSP) is a reported 900 MW closed-loop pumped-storage project in Ayodhya Hills, Bagmundi block, Purulia District, West Bengal. Its stated works include reservoirs and dams, water conductors, an underground powerhouse and transformer cavern, and associated transmission and switchyard infrastructure. Main works were completed on 17.12.2007; the page states commissioning in 2007.

Evidence limits and unknowns

The supplied project text does not identify a current procurement, retrofit package, supplier package, or buying window.

Project milestones

Attributed project events and plans. Source report dates and dossier release dates are separate.

  1. Main project work · Work began

    Reported event · date precision: month

    Not independently corroborated.

    This source report does not establish current progress.

    Technical record for this milestone

    Recorded event date: May 2002

    Released statement reference: released-date:date:work_started

    Derived from the reviewed date statement; this is not a verbatim source quotation.

    Main project work started in May 2002 and was completed on 17.12.2007, ahead of the scheduled completion date of 31.12.2007. The page states the project was commissioned in 2007.

    attribution
    portal.wbsedcl.in

    Source published not recorded · observed 2026-10-17

    Source revision: da9e24a9-6bc3-4f7d-a6f5-4ee7ed9699b7

  2. Project · Commissioning reported

    Reported event · date precision: year

    Not independently corroborated.

    This source report does not establish current progress.

    Commissioning is reported only to the year; no exact commissioning date is established. Its order relative to main-work completion within that year is not established.

    Technical record for this milestone

    Recorded event date: 2007

    Released statement reference: released-date:date:commissioned

    Derived from the reviewed date statement; this is not a verbatim source quotation.

    Main project work started in May 2002 and was completed on 17.12.2007, ahead of the scheduled completion date of 31.12.2007. The page states the project was commissioned in 2007.

    attribution
    portal.wbsedcl.in

    Source published not recorded · observed 2026-10-17

    Source revision: da9e24a9-6bc3-4f7d-a6f5-4ee7ed9699b7

  3. Main project work · Completed

    Reported event · date precision: day

    Not independently corroborated.

    This source report does not establish current progress.

    The same statement gives a historical scheduled completion deadline of 31.12.2007; it is not an outstanding forecast.

    Technical record for this milestone

    Recorded event date: 17.12.2007

    Released statement reference: released-date:date:work_completed

    Derived from the reviewed date statement; this is not a verbatim source quotation.

    Main project work started in May 2002 and was completed on 17.12.2007, ahead of the scheduled completion date of 31.12.2007. The page states the project was commissioned in 2007.

    attribution
    portal.wbsedcl.in

    Source published not recorded · observed 2026-10-17

    Source revision: da9e24a9-6bc3-4f7d-a6f5-4ee7ed9699b7

Is this project a fit for your company?

Check how this project relates to what your company supplies, with evidence gaps and a next step.

Create your account for free and include your business details to get custom commercial assessments.

Project metadata

Country
India
Based on reviewed release evidence
Region
Asia
Category
Energy
Derived from released evidence
Physical assets
Electricity Transmission, Pumped Hydro

Based on this release's supporting evidence. Unresolved fields remain unclassified; these labels do not establish current progress or a buying window.

Released facts and supporting evidence

Each fact retains its source, uncertainty and time context. If a publisher page moves or is unavailable, use the recorded quotation and observation date below.

Date

Reported as actual

Main project work started in May 2002 and was completed on 17.12.2007, ahead of the scheduled completion date of 31.12.2007. The page states the project was commissioned in 2007.

Attributed to portal.wbsedcl.in.

Source: portal.wbsedcl.in · publication date not recorded · observed 2026-10-17

Sources and evidence · portal.wbsedcl.in
Source published: Not recordedObserved: 2026-10-17

portal.wbsedcl.in
Attributed to portal.wbsedcl.in

Technical record · Main project work started in May 2002 and …
Evidence location
/html/body/section[3]/div/div/div/div[2]/p[2]
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
c51af7d4-2f43-4400-a2ab-b9eefd117311
Evidence reference
3c82a613-42e2-43af-9690-2e180abf2087
Source revision
da9e24a9-6bc3-4f7d-a6f5-4ee7ed9699b7
Content fingerprint
41a9f51a8269c94e5a201d64238edd0889fb6cdff78379145557e083839e7db7
Source address
https://portal.wbsedcl.in/irj/go/km/docs/internet/new_website/PPSP.html

Project name

Source reported

Purulia Pumped Storage Project (PPSP)

Attributed to portal.wbsedcl.in.

Source: portal.wbsedcl.in · publication date not recorded · observed 2026-10-17

Sources and evidence · portal.wbsedcl.in
Source published: Not recordedObserved: 2026-10-17

portal.wbsedcl.in
Attributed to portal.wbsedcl.in

Technical record · Purulia Pumped Storage Project (PPSP)
Evidence location
/html/body/section[3]/div/div/div/div[2]/h2
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
fda8bb2e-95a3-4c6e-b03a-b4d67e738c2b
Evidence reference
cdad048c-2970-4e86-973d-49d772be915e
Source revision
da9e24a9-6bc3-4f7d-a6f5-4ee7ed9699b7
Content fingerprint
41a9f51a8269c94e5a201d64238edd0889fb6cdff78379145557e083839e7db7
Source address
https://portal.wbsedcl.in/irj/go/km/docs/internet/new_website/PPSP.html

Scope

Source reported

A closed-loop pumped-storage plant with 900 MW installed capacity (4 × 225 MW). The physical works include upper and lower rockfill dams and reservoirs, twin water conductors, an underground powerhouse with four reversible vertical Francis pump-turbines, an underground transformer cavern with four main transformers, an access tunnel, a 400 kV gas-insulated switchyard, a cable tunnel, and two 400 kV double-circuit transmission lines connected with Durgapur and New PPSP substations.

Attributed to portal.wbsedcl.in.

Source: portal.wbsedcl.in · publication date not recorded · observed 2026-10-17

Sources and evidence · portal.wbsedcl.in
Source published: Not recordedObserved: 2026-10-17

portal.wbsedcl.in
Attributed to portal.wbsedcl.in

Technical record · A closed-loop pumped-storage plant with 900 MW installed …
Evidence location
/html/body/section[3]/div/div/div/div[2]/p[1]
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
02c60d34-e293-41de-b613-5734b62694da
Evidence reference
b466a9c3-770d-49ab-a55d-5c8393785adc
Source revision
da9e24a9-6bc3-4f7d-a6f5-4ee7ed9699b7
Content fingerprint
41a9f51a8269c94e5a201d64238edd0889fb6cdff78379145557e083839e7db7
Source address
https://portal.wbsedcl.in/irj/go/km/docs/internet/new_website/PPSP.html

Sector

Source reported

Pumped-storage hydroelectric power.

Attributed to portal.wbsedcl.in.

Source: portal.wbsedcl.in · publication date not recorded · observed 2026-10-17

Sources and evidence · portal.wbsedcl.in
Source published: Not recordedObserved: 2026-10-17

portal.wbsedcl.in
Attributed to portal.wbsedcl.in

Technical record · Pumped-storage hydroelectric power.
Evidence location
/html/body/section[3]/div/div/div/div[2]/p[1]
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
56672dad-be2e-4f02-a82f-853194f08443
Evidence reference
b466a9c3-770d-49ab-a55d-5c8393785adc
Source revision
da9e24a9-6bc3-4f7d-a6f5-4ee7ed9699b7
Content fingerprint
41a9f51a8269c94e5a201d64238edd0889fb6cdff78379145557e083839e7db7
Source address
https://portal.wbsedcl.in/irj/go/km/docs/internet/new_website/PPSP.html

Funding

Source reported

The page says project cost was funded through loan assistance from the Japan Bank for International Cooperation (JICA) and a grant from the Government of West Bengal.

Attributed to portal.wbsedcl.in.

Source: portal.wbsedcl.in · publication date not recorded · observed 2026-10-17

Sources and evidence · portal.wbsedcl.in
Source published: Not recordedObserved: 2026-10-17

portal.wbsedcl.in
Attributed to portal.wbsedcl.in

Technical record · The page says project cost was funded through …
Evidence location
/html/body/section[3]/div/div/div/div[2]/p[2]/text-position:100
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
7867f201-2405-41ee-ace3-2d03ef5f29cd
Evidence reference
3f71f22e-cb18-43b7-a81d-f15c28e8eff9
Source revision
da9e24a9-6bc3-4f7d-a6f5-4ee7ed9699b7
Content fingerprint
41a9f51a8269c94e5a201d64238edd0889fb6cdff78379145557e083839e7db7
Source address
https://portal.wbsedcl.in/irj/go/km/docs/internet/new_website/PPSP.html

Current activity

Source reported

The page states that PPSP units operate in generation, pumping, and synchronous-condenser modes.

Attributed to portal.wbsedcl.in.

Source: portal.wbsedcl.in · publication date not recorded · observed 2026-10-17

Sources and evidence · portal.wbsedcl.in
Source published: Not recordedObserved: 2026-10-17

portal.wbsedcl.in
Attributed to portal.wbsedcl.in

Technical record · The page states that PPSP units operate in …
Evidence location
/html/body/section[3]/div/div/div/div[2]/br[18]/text-position:108
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
218fea42-3417-411b-8340-2ab027842264
Evidence reference
8a54829b-8cc7-4563-9451-775f92bf0d4e
Source revision
da9e24a9-6bc3-4f7d-a6f5-4ee7ed9699b7
Content fingerprint
41a9f51a8269c94e5a201d64238edd0889fb6cdff78379145557e083839e7db7
Source address
https://portal.wbsedcl.in/irj/go/km/docs/internet/new_website/PPSP.html

Location

Source reported

Ayodhya Hills region, under the Bagmundi block, Purulia District, West Bengal, India.

Attributed to portal.wbsedcl.in.

Source: portal.wbsedcl.in · publication date not recorded · observed 2026-10-17

Sources and evidence · portal.wbsedcl.in
Source published: Not recordedObserved: 2026-10-17

portal.wbsedcl.in
Attributed to portal.wbsedcl.in

Technical record · Ayodhya Hills region, under the Bagmundi block, Purulia …
Evidence location
/html/body/section[3]/div/div/div/div[2]/p[1]/text-position:97
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
b4c48d87-9fd9-4782-a3b7-5a26526a60f5
Evidence reference
4ea8922b-4559-432f-bdf3-f1b7668b302b
Source revision
da9e24a9-6bc3-4f7d-a6f5-4ee7ed9699b7
Content fingerprint
41a9f51a8269c94e5a201d64238edd0889fb6cdff78379145557e083839e7db7
Source address
https://portal.wbsedcl.in/irj/go/km/docs/internet/new_website/PPSP.html

Investment estimate

Source reported

Reported project completion cost: Rs 2491.38 crore, against a revised project cost of Rs 2952 crore.

Attributed to portal.wbsedcl.in.

Source: portal.wbsedcl.in · publication date not recorded · observed 2026-10-17

Sources and evidence · portal.wbsedcl.in
Source published: Not recordedObserved: 2026-10-17

portal.wbsedcl.in
Attributed to portal.wbsedcl.in

Technical record · Reported project completion cost: Rs 2491.38 crore, against …
Evidence location
/html/body/section[3]/div/div/div/div[2]/p[2]
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
2408d897-e189-4adf-9fc7-e7253b912294
Evidence reference
3c82a613-42e2-43af-9690-2e180abf2087
Source revision
da9e24a9-6bc3-4f7d-a6f5-4ee7ed9699b7
Content fingerprint
41a9f51a8269c94e5a201d64238edd0889fb6cdff78379145557e083839e7db7
Source address
https://portal.wbsedcl.in/irj/go/km/docs/internet/new_website/PPSP.html
Source report history

Prior and superseded states remain labelled. Dates below identify source publication when known, otherwise source observation. They are not assumed event dates; each fact retains its own time qualifications.

  1. No material timeline events have been released.

Follow this project

Get project updates by email when new information is published.

Follow for free without an account, with the option to unsubscribe anytime. We'll email you a link to confirm.

DEEPRFP, S.L.U. uses your email and selected project to confirm and deliver the updates you request. You can stop anytime. Product news needs a separate opt-in. Read the Privacy Policy for legal bases, recipients, retention, your rights and contact details.