Skip to content
Menu
CapexCue · Public evidence · Printed 11 Nov 2026
Explore projects / Project dossier

Remplacement du pont ferroviaire sur la Seine à Varennes-sur-Seine et la Grande Paroisse

France · Transport and logistics

In-depth research Release 1

Project scope

Plan: Replace the existing three-span metallic railway bridge, about 143 m long, with a new deck of steel beams integrated into concrete for ballasted track. The new deck is specified as 143.92 m long, compared with 142.80 m for the existing deck, and is intended to increase clearance below the bridge by 49 cm to 6.1 m. The existing supports are to be retained and their foundations strengthened: 12 piles are specified for the Varennes-sur-Seine C3 abutment, while other supports are to be reinforced by cement-grout injection. Separately, the opinion records a temporary river-pile discrepancy: the dossier indicated 32 piles in the major riverbed, while the latest sizing was said to require 8–12; this is distinct from the 12 piles specified at C3.

Reported status and procurement

Reported development

Plan: The opinion described works lasting about two years, with a planned start in January 2026, deck replacement targeted for August 2027 and completion planned for January 2028. Three work areas were planned: a main area on Haropa Port land at Varennes-sur-Seine, a secondary area on the Varennes-sur-Seine side and a connected area at La Grande Paroisse. River transport was to be prioritised, with land access also planned. Enabling works included temporary supports and pontoons, about 450 m³ of dredging near La Grande Paroisse, and demolition of disused railway structure OA1 to provide access; OA1 was not to be rebuilt. The opinion also described nine night-time rail interruptions, a full 16-day rail closure, and a three-day interruption to river traffic. These are plans reported in 2025, not confirmation that works occurred.

Procurement availability
Unknown / not established

Reported regulatory context

A case-by-case decision dated 17 September 2020 required environmental assessment. The opinion reports an application for environmental authorisation under water legislation and a dossier seeking derogation from protections for protected species and their habitats. The environmental authority's opinion, adopted on 24 July 2025, assesses the impact study and environmental treatment; it is expressly neither favourable nor unfavourable and is not itself an authorisation decision.

A source report alone does not establish current progress or an open buying window.

Project summary

Remplacement du pont ferroviaire sur la Seine à Varennes-sur-Seine et la Grande Paroisse

SNCF Réseau’s project is to replace a three-span metallic railway bridge, about 143 m long, across the Seine between Varennes-sur-Seine and La Grande Paroisse. The bridge carries line 746000 between Corbeil-Essonnes and Montereau, used by suburban, regional and freight trains. The planned replacement is a steel-beam deck integrated into concrete for ballasted track, with the existing supports retained and their foundations strengthened. The 12 piles specified for the C3 abutment are separate from the river-pile figures: the dossier listed 32 piles in the Seine’s floodplain, while the latest sizing reported to the authority’s rapporteurs indicated that 8–12 should be needed there.

The environmental authority opinion adopted on 24 July 2025 described an approximately two-year works plan, with a January 2026 start planned, deck replacement targeted for August 2027 and completion planned for January 2028. These are planned dates reported in 2025, not confirmation that the works occurred. The opinion described three work areas and stated that river access would be prioritised, with land access also planned.

The operation was estimated at about €52 million excluding tax, including €38 million for the bridge. The estimate was supplied orally to the rapporteurs during their site visit; its value year and the share attributable to environmental measures were not specified in the dossier. The opinion noted that the project’s ecological assessment and mitigation still needed updates: although the dossier assessed residual effects on protected species as not significant, the authority called for compensation and an updated derogation dossier for several groups, and said effects on the protected thick-shelled river mussel from river works could not be ruled out. The opinion assesses the impact study and environmental treatment; it is expressly neither favourable nor unfavourable and is not an authorisation decision.

Evidence limits and unknowns

The opinion adopted on 24 July 2025 gives planned dates but does not establish whether the works started, their current status, or whether they were completed.

The supplied opinion does not establish the outcomes of the environmental-authorisation or protected-species derogation procedures.

The final number of piles in the river is not established: the dossier listed 32 in the floodplain, while the latest sizing indicated 8–12. The opinion later reported that the proposed vessel waiting area was abandoned, while an existing right-bank area was under discussion as an alternative; it does not establish the final arrangement.

The opinion does not confirm final ecological survey results, compensation decisions, or completion of the proposed 30-year management agreement for the wetland compensation site.

The supplied opinion does not identify a contractor, procurement award, or financing arrangement.

Is this project a fit for your company?

Check how this project relates to what your company supplies, with evidence gaps and a next step.

Create your account for free and include your business details to get custom commercial assessments.

Project metadata

Country
France
Based on reviewed release evidence
Region
Europe
Category
Transport and logistics
Derived from released evidence
Physical assets
Railway

Based on this release's supporting evidence. Unresolved fields remain unclassified; these labels do not establish current progress or a buying window.

Released facts and supporting evidence

Each fact retains its source, uncertainty and time context. If a publisher page moves or is unavailable, use the recorded quotation and observation date below.

Project name

Source reported

Remplacement du pont ferroviaire sur la Seine à Varennes-sur-Seine et la Grande Paroisse

Attributed to IGEDD environmental authority assessment and attributed developer synthesis.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-03

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-03

IGEDD environmental authority native opinion text
Attributed to IGEDD environmental authority assessment and attributed developer synthesis

Technical record · Remplacement du pont ferroviaire sur la Seine à …
Evidence location
page:2
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
67a23a1a-4dd2-4303-8620-947424ee8015
Evidence reference
fb424794-4acc-40c4-85ee-a0ceeae1e015
Source revision
0039e72b-b2c0-4662-ad28-e7a830626eb2
Content fingerprint
47e24fc910d70d53f344c3617af692fb842970efbe0c3472b3e7d9dbe4ace7af
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/07_-_projet_de_remplacement_du_pont-rail_entre_varennes-sur-seine_et_la_grande-paroisse_77__cle67e913.pdf

Scope

Planned

Replace the existing three-span metallic railway bridge, about 143 m long, with a new deck of steel beams integrated into concrete for ballasted track. The new deck is specified as 143.92 m long, compared with 142.80 m for the existing deck, and is intended to increase clearance below the bridge by 49 cm to 6.1 m. The existing supports are to be retained and their foundations strengthened: 12 piles are specified for the Varennes-sur-Seine C3 abutment, while other supports are to be reinforced by cement-grout injection. Separately, the opinion records a temporary river-pile discrepancy: the dossier indicated 32 piles in the major riverbed, while the latest sizing was said to require 8–12; this is distinct from the 12 piles specified at C3.

Attributed to IGEDD environmental authority assessment and attributed developer synthesis.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-03

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-03

IGEDD environmental authority native opinion text
Attributed to IGEDD environmental authority assessment and attributed developer synthesis

Technical record · Replace the existing three-span metallic railway bridge, about …
Evidence location
page:5
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
20d1de48-fda6-4684-8387-47c2f9f99733
Evidence reference
77a4afe9-20b3-47e9-95df-6dd114700b87
Source revision
0039e72b-b2c0-4662-ad28-e7a830626eb2
Content fingerprint
47e24fc910d70d53f344c3617af692fb842970efbe0c3472b3e7d9dbe4ace7af
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/07_-_projet_de_remplacement_du_pont-rail_entre_varennes-sur-seine_et_la_grande-paroisse_77__cle67e913.pdf

Project ecology

Source reported

The Seine section, banks and some downstream woodland and agricultural areas are within the Natura 2000 site “Bassée et plaines adjacentes”; the secondary and connected work areas are included. The project is also within the ZNIEFF type II “Vallée de la Seine entre Vernou et Montereau,” except for the main work area. The connected work-area footprint, partly within a wetland, was reduced from 0.44 ha to about 0.1 ha; the opinion does not establish that 0.1 ha is the area of wetland affected. A separate 0.65 ha compensation site about 350 m away in Varennes-sur-Seine was proposed for conversion from poplar cultivation to willow and alder woodland, with reedbeds preserved and a filled area removed. An agreement with the landowner was still being negotiated, and the authority sought confirmation of 30 years of management. The dossier assessed residual effects on protected species as not significant, but the authority considered that assessment inadequate for several groups given the two-year works and called for compensation and an updated protected-species derogation dossier. Effects on the protected thick-shelled river mussel from river works could not be ruled out. The opinion also records evolving barge waiting-area arrangements: abandonment of proposed waiting-area dolphins had been indicated but needed confirmation or a complete avoidance, reduction and compensation approach; use of an existing right-bank area was under discussion. This does not establish the final waiting-area arrangement, and the proposed loading pontoon and other river works are distinct from that unresolved arrangement. Further ecological survey and follow-up information was also needed.

Attributed to IGEDD environmental authority assessment and attributed developer synthesis.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-03

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-03

IGEDD environmental authority native opinion text
Attributed to IGEDD environmental authority assessment and attributed developer synthesis

Technical record · The Seine section, banks and some downstream woodland …
Evidence location
page:7
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
a26af08f-6d41-438e-83ed-9d42899077cf
Evidence reference
1bb5b0c9-d543-4089-aa42-4fc57da2c595
Source revision
0039e72b-b2c0-4662-ad28-e7a830626eb2
Content fingerprint
47e24fc910d70d53f344c3617af692fb842970efbe0c3472b3e7d9dbe4ace7af
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/07_-_projet_de_remplacement_du_pont-rail_entre_varennes-sur-seine_et_la_grande-paroisse_77__cle67e913.pdf

Delivery

Planned

The opinion described works lasting about two years, with a planned start in January 2026, deck replacement targeted for August 2027 and completion planned for January 2028. Three work areas were planned: a main area on Haropa Port land at Varennes-sur-Seine, a secondary area on the Varennes-sur-Seine side and a connected area at La Grande Paroisse. River transport was to be prioritised, with land access also planned. Enabling works included temporary supports and pontoons, about 450 m³ of dredging near La Grande Paroisse, and demolition of disused railway structure OA1 to provide access; OA1 was not to be rebuilt. The opinion also described nine night-time rail interruptions, a full 16-day rail closure, and a three-day interruption to river traffic. These are plans reported in 2025, not confirmation that works occurred.

Attributed to IGEDD environmental authority assessment and attributed developer synthesis.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-03

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-03

IGEDD environmental authority native opinion text
Attributed to IGEDD environmental authority assessment and attributed developer synthesis

Technical record · The opinion described works lasting about two years, …
Evidence location
page:6
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
cdde9dc0-d1b1-4072-9cde-9ed9727fef57
Evidence reference
084b456d-2785-436a-b540-51fe884060cf
Source revision
0039e72b-b2c0-4662-ad28-e7a830626eb2
Content fingerprint
47e24fc910d70d53f344c3617af692fb842970efbe0c3472b3e7d9dbe4ace7af
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/07_-_projet_de_remplacement_du_pont-rail_entre_varennes-sur-seine_et_la_grande-paroisse_77__cle67e913.pdf

Location

Source reported

Across the Seine between Varennes-sur-Seine and La Grande Paroisse, in Seine-et-Marne (department 77).

Attributed to IGEDD environmental authority assessment and attributed developer synthesis.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-03

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-03

IGEDD environmental authority native opinion text
Attributed to IGEDD environmental authority assessment and attributed developer synthesis

Technical record · Across the Seine between Varennes-sur-Seine and La Grande …
Evidence location
page:4
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
9d4a8dac-9797-4138-b27a-a7dec80dd10f
Evidence reference
fed44732-1641-418c-8183-b497aa0af02e
Source revision
0039e72b-b2c0-4662-ad28-e7a830626eb2
Content fingerprint
47e24fc910d70d53f344c3617af692fb842970efbe0c3472b3e7d9dbe4ace7af
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/07_-_projet_de_remplacement_du_pont-rail_entre_varennes-sur-seine_et_la_grande-paroisse_77__cle67e913.pdf

Developer

Source reported

SNCF Réseau is identified as the project owner (maître d’ouvrage).

Attributed to IGEDD environmental authority assessment and attributed developer synthesis.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-03

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-03

IGEDD environmental authority native opinion text
Attributed to IGEDD environmental authority assessment and attributed developer synthesis

Technical record · SNCF Réseau is identified as the project owner …
Evidence location
page:3
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
e227986a-9b86-44b5-87bf-99401d24d8a6
Evidence reference
61dcf521-d0f1-44cb-8685-e0ed5ea41267
Source revision
0039e72b-b2c0-4662-ad28-e7a830626eb2
Content fingerprint
47e24fc910d70d53f344c3617af692fb842970efbe0c3472b3e7d9dbe4ace7af
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/07_-_projet_de_remplacement_du_pont-rail_entre_varennes-sur-seine_et_la_grande-paroisse_77__cle67e913.pdf

Investment estimate

Source reported

Estimated at approximately €52 million excluding tax, including €38 million excluding tax for the bridge. The estimate's value year and the portion attributable to environmental measures were not specified in the dossier.

Attributed to IGEDD environmental authority assessment and attributed developer synthesis.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-03

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-03

IGEDD environmental authority native opinion text
Attributed to IGEDD environmental authority assessment and attributed developer synthesis

Technical record · Estimated at approximately €52 million excluding tax, including …
Evidence location
page:8
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
b040219c-270a-412c-b738-14b8f6f4b3bf
Evidence reference
fea08919-4aac-45a4-aa27-19b7b283b182
Source revision
0039e72b-b2c0-4662-ad28-e7a830626eb2
Content fingerprint
47e24fc910d70d53f344c3617af692fb842970efbe0c3472b3e7d9dbe4ace7af
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/07_-_projet_de_remplacement_du_pont-rail_entre_varennes-sur-seine_et_la_grande-paroisse_77__cle67e913.pdf

Regulatory evidence

Source reported

A case-by-case decision dated 17 September 2020 required environmental assessment. The opinion reports an application for environmental authorisation under water legislation and a dossier seeking derogation from protections for protected species and their habitats. The environmental authority's opinion, adopted on 24 July 2025, assesses the impact study and environmental treatment; it is expressly neither favourable nor unfavourable and is not itself an authorisation decision.

Attributed to IGEDD environmental authority assessment and attributed developer synthesis.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-03

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-03

IGEDD environmental authority native opinion text
Attributed to IGEDD environmental authority assessment and attributed developer synthesis

Technical record · A case-by-case decision dated 17 September 2020 required …
Evidence location
page:2
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
9de3a71b-6372-48bf-a94b-0544c1f70c03
Evidence reference
fb424794-4acc-40c4-85ee-a0ceeae1e015
Source revision
0039e72b-b2c0-4662-ad28-e7a830626eb2
Content fingerprint
47e24fc910d70d53f344c3617af692fb842970efbe0c3472b3e7d9dbe4ace7af
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/07_-_projet_de_remplacement_du_pont-rail_entre_varennes-sur-seine_et_la_grande-paroisse_77__cle67e913.pdf
Source report history

Prior and superseded states remain labelled. Dates below identify source publication when known, otherwise source observation. They are not assumed event dates; each fact retains its own time qualifications.

  1. No material timeline events have been released.

Follow this project

Get project updates by email when new information is published.

Follow for free without an account, with the option to unsubscribe anytime. We'll email you a link to confirm.

DEEPRFP, S.L.U. uses your email and selected project to confirm and deliver the updates you request. You can stop anytime. Product news needs a separate opt-in. Read the Privacy Policy for legal bases, recipients, retention, your rights and contact details.