Stigler Lake Dam Rehabilitation Project

United States · Water and environment

In-depth research Release 1

Project scope

Plan: The proposed action is rehabilitation of Stigler Lake Dam and an associated raw-water pipeline for the Stigler Water Treatment Plant during dam construction. The FONSI describes connecting an existing waterline to the plant, and also describes a new pipeline segment running from an existing raw-water pipeline to the plant. It does not further clarify the precise configuration of that connection.

Reported status and procurement

Reported development

Plan: During dam construction, the treatment plant would be unable to take water from Stigler Lake. The proposed 12-inch-diameter pipeline would convey raw water approximately 5,135 feet from an existing pipeline originating at Lake John Wells directly to the treatment plant to maintain its operation. The source does not report that construction has commenced or been completed.

Procurement availability
Unknown / not established

Reported regulatory context

Reclamation issued a FONSI, finding that the project is not a major Federal action significantly affecting the human environment and that an Environmental Impact Statement is not required; the EA considered No Action and Proposed Action alternatives. The source reports USACE authorization on May 23, 2025, for discharge of fill material into waters of the United States under Nationwide Permits 3 and 58, and states that Section 404 requirements and ODEQ-approved Section 401 Water Quality Certification conditions apply. The City is required to obtain an OKR10 Construction Stormwater Permit before construction and to develop and implement a stormwater pollution prevention plan. On January 8, 2025, SHPO agreed with the assessment that there are no known historic properties affected within the APE; on February 10, 2025, OAS agreed with findings concerning the absence of effects on prehistoric archaeological resources. These are qualified findings: if historic properties or resources are encountered during construction, the City must halt work in their vicinity and notify Reclamation; work may resume only after Reclamation completes SHPO consultation and any appropriate protective measures are implemented. The FONSI reports these determinations and requirements but does not establish the current status of every required permit or condition.

Reported financing

The City applied for and received a federal grant through Reclamation’s Drought Resiliency Program, and Reclamation says it is providing project funding. The source gives no grant amount, disbursement details, or total project cost.

A source report alone does not establish current progress or an open buying window.

Project summary

The Stigler Lake Dam Rehabilitation Project is proposed by the City of Stigler in Haskell County, Oklahoma. A June 2025 FONSI describes planned seepage-control and slope work, spillway rehabilitation, and a proposed raw-water pipeline to maintain treatment-plant operation during dam construction. Reclamation reports providing project funding and that the City received a grant through its Drought Resiliency Program. The FONSI reports USACE authorization dated May 23, 2025, and requires the City to obtain an OKR10 Construction Stormwater Permit before construction.

Evidence limits and unknowns

The June 2025 FONSI does not state whether construction has started, is ongoing, or has been completed.

The FONSI requires an OKR10 Construction Stormwater Permit before construction but does not state whether it has since been obtained.

The FONSI identifies FNI's 2023 design contract but does not identify a construction contractor or report procurement status or packages.

The source gives no grant amount, total project cost, or funding disbursement details.

The FONSI describes the pipeline connection both as connecting an existing waterline and as a new segment from an existing raw-water pipeline; it does not clarify the precise configuration.

The supplied evidence covers the June 2025 FONSI; it references an attached or incorporated environmental assessment, whose full text is not separately included in the supplied pages. Graphical content was not interpreted (u0001–u0008; EA reference at u0003).

The FONSI reports permit and consultation determinations as of its text but does not establish whether requirements or conditions have changed since June 2025.

Is this project a fit for your company?

Check how this project relates to what your company supplies, with evidence gaps and a next step.

Create your account for free and include your business details to get custom commercial assessments.

Project metadata

Country
United States
Based on reviewed release evidence
Region
North America
Category
Water and environment
Derived from released evidence
Physical assets
Drinking Water

Based on this release's supporting evidence. Unresolved fields remain unclassified; these labels do not establish current progress or a buying window.

Released facts and supporting evidence

Each fact retains its source, uncertainty and time context. If a publisher page moves or is unavailable, use the recorded quotation and observation date below.

Project name

Source reported

Stigler Lake Dam Rehabilitation Project

Attributed to US Bureau of Reclamation own-government project narrative.

Source: US Bureau of Reclamation screened government project narrative · publication date not recorded · observed 2026-10-02

Sources and evidence · US Bureau of Reclamation screened government project narrative
Source published: Not recordedObserved: 2026-10-02

US Bureau of Reclamation screened government project narrative
Attributed to US Bureau of Reclamation own-government project narrative

Technical record · Stigler Lake Dam Rehabilitation Project
Evidence location
page:1
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
f4f16ddb-5850-4c28-b110-d7f0e8de1257
Evidence reference
e30921e0-58d5-4c7a-bd29-3403f8508351
Source revision
b47fa43f-1cc3-4f20-ae97-50c5c3d4d4ad
Content fingerprint
8560cc0966ca088fc39f9f825c207cbe105906b25b8d8e704fabcdb92c86b7f3
Source address
https://www.usbr.gov/gp/nepa/stigler_fonsi.pdf

Scope

Planned

The proposed action is rehabilitation of Stigler Lake Dam and an associated raw-water pipeline for the Stigler Water Treatment Plant during dam construction. The FONSI describes connecting an existing waterline to the plant, and also describes a new pipeline segment running from an existing raw-water pipeline to the plant. It does not further clarify the precise configuration of that connection.

Attributed to US Bureau of Reclamation own-government project narrative.

Source: US Bureau of Reclamation screened government project narrative · publication date not recorded · observed 2026-10-02

Sources and evidence · US Bureau of Reclamation screened government project narrative
Source published: Not recordedObserved: 2026-10-02

US Bureau of Reclamation screened government project narrative
Attributed to US Bureau of Reclamation own-government project narrative

Technical record · The proposed action is rehabilitation of Stigler Lake …
Evidence location
page:4
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
14db7c3e-4cf1-4288-a500-419bed96de66
Evidence reference
a8edcd44-2313-40e9-9704-1850ed7b1e38
Source revision
b47fa43f-1cc3-4f20-ae97-50c5c3d4d4ad
Content fingerprint
8560cc0966ca088fc39f9f825c207cbe105906b25b8d8e704fabcdb92c86b7f3
Source address
https://www.usbr.gov/gp/nepa/stigler_fonsi.pdf

Current activity

Planned

Proposed dam works include a soil-cement bentonite cutoff wall seated in underlying sandstone to control seepage; a toe drain and compacted fill to flatten the downstream slope to 3H:1V; compacted fill to flatten the upstream slope to 2H:1V; and rock riprap for erosion protection. The spillway rehabilitation is within the existing footprint. The source describes an existing 74-foot-long concrete-lined channel and 72-foot-wide concrete weir, with the rehabilitated weir remaining at elevation 625.9 feet msl. The improved channel is specified with a 12-inch concrete slab, 64-foot bottom width, and 4H:1V side slopes. The existing dam is described as an approximately 1,860-foot earthen embankment with a maximum height of 40 feet.

Attributed to US Bureau of Reclamation own-government project narrative.

Source: US Bureau of Reclamation screened government project narrative · publication date not recorded · observed 2026-10-02

Sources and evidence · US Bureau of Reclamation screened government project narrative
Source published: Not recordedObserved: 2026-10-02

US Bureau of Reclamation screened government project narrative
Attributed to US Bureau of Reclamation own-government project narrative

Technical record · Proposed dam works include a soil-cement bentonite cutoff …
Evidence location
page:4
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
d9e1e960-a30d-4f8b-9dae-0015b264d299
Evidence reference
cabb2504-f956-42ba-bb8a-1029d8c6d9dc
Source revision
b47fa43f-1cc3-4f20-ae97-50c5c3d4d4ad
Content fingerprint
8560cc0966ca088fc39f9f825c207cbe105906b25b8d8e704fabcdb92c86b7f3
Source address
https://www.usbr.gov/gp/nepa/stigler_fonsi.pdf

Delivery

Planned

During dam construction, the treatment plant would be unable to take water from Stigler Lake. The proposed 12-inch-diameter pipeline would convey raw water approximately 5,135 feet from an existing pipeline originating at Lake John Wells directly to the treatment plant to maintain its operation. The source does not report that construction has commenced or been completed.

Attributed to US Bureau of Reclamation own-government project narrative.

Source: US Bureau of Reclamation screened government project narrative · publication date not recorded · observed 2026-10-02

Sources and evidence · US Bureau of Reclamation screened government project narrative
Source published: Not recordedObserved: 2026-10-02

US Bureau of Reclamation screened government project narrative
Attributed to US Bureau of Reclamation own-government project narrative

Technical record · During dam construction, the treatment plant would be …
Evidence location
page:4
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
7736b4e5-cbee-4a4b-a865-c476cdda7c85
Evidence reference
a32e0bb5-48d4-4055-8174-7d636fc72c25
Source revision
b47fa43f-1cc3-4f20-ae97-50c5c3d4d4ad
Content fingerprint
8560cc0966ca088fc39f9f825c207cbe105906b25b8d8e704fabcdb92c86b7f3
Source address
https://www.usbr.gov/gp/nepa/stigler_fonsi.pdf

Location

Source reported

The project area is in Haskell County, Oklahoma, at 35.241258°N, -95.113529°W.

Attributed to US Bureau of Reclamation own-government project narrative.

Source: US Bureau of Reclamation screened government project narrative · publication date not recorded · observed 2026-10-02

Sources and evidence · US Bureau of Reclamation screened government project narrative
Source published: Not recordedObserved: 2026-10-02

US Bureau of Reclamation screened government project narrative
Attributed to US Bureau of Reclamation own-government project narrative

Technical record · The project area is in Haskell County, Oklahoma, …
Evidence location
page:4
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
b27c0cbb-77dc-4cde-90a5-c853580331fc
Evidence reference
9ee6f744-fb4a-4e4b-8e8d-ac214fab87d3
Source revision
b47fa43f-1cc3-4f20-ae97-50c5c3d4d4ad
Content fingerprint
8560cc0966ca088fc39f9f825c207cbe105906b25b8d8e704fabcdb92c86b7f3
Source address
https://www.usbr.gov/gp/nepa/stigler_fonsi.pdf

Developer

Planned

The City of Stigler is the project proponent identified as proposing the dam rehabilitation and associated waterline connection.

Attributed to US Bureau of Reclamation own-government project narrative.

Source: US Bureau of Reclamation screened government project narrative · publication date not recorded · observed 2026-10-02

Sources and evidence · US Bureau of Reclamation screened government project narrative
Source published: Not recordedObserved: 2026-10-02

US Bureau of Reclamation screened government project narrative
Attributed to US Bureau of Reclamation own-government project narrative

Technical record · The City of Stigler is the project proponent …
Evidence location
page:4
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
7566da65-9b10-4efd-84e3-7b2ca16f950c
Evidence reference
19e11a3e-65ef-425c-9f11-f88241d96616
Source revision
b47fa43f-1cc3-4f20-ae97-50c5c3d4d4ad
Content fingerprint
8560cc0966ca088fc39f9f825c207cbe105906b25b8d8e704fabcdb92c86b7f3
Source address
https://www.usbr.gov/gp/nepa/stigler_fonsi.pdf

Contractor

Source reported

The City contracted Freese and Nichols, Inc. (FNI) in 2023 to design improvements. The source does not identify a construction contractor.

Attributed to US Bureau of Reclamation own-government project narrative.

Source: US Bureau of Reclamation screened government project narrative · publication date not recorded · observed 2026-10-02

Sources and evidence · US Bureau of Reclamation screened government project narrative
Source published: Not recordedObserved: 2026-10-02

US Bureau of Reclamation screened government project narrative
Attributed to US Bureau of Reclamation own-government project narrative

Technical record · The City contracted Freese and Nichols, Inc. (FNI) …
Evidence location
page:3
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
7c27a134-14f2-4277-a768-2a6f144b6b46
Evidence reference
5fb6b367-c7d0-4fca-a934-58f0ccdce25c
Source revision
b47fa43f-1cc3-4f20-ae97-50c5c3d4d4ad
Content fingerprint
8560cc0966ca088fc39f9f825c207cbe105906b25b8d8e704fabcdb92c86b7f3
Source address
https://www.usbr.gov/gp/nepa/stigler_fonsi.pdf

Regulatory evidence

Source reported

Reclamation issued a FONSI, finding that the project is not a major Federal action significantly affecting the human environment and that an Environmental Impact Statement is not required; the EA considered No Action and Proposed Action alternatives. The source reports USACE authorization on May 23, 2025, for discharge of fill material into waters of the United States under Nationwide Permits 3 and 58, and states that Section 404 requirements and ODEQ-approved Section 401 Water Quality Certification conditions apply. The City is required to obtain an OKR10 Construction Stormwater Permit before construction and to develop and implement a stormwater pollution prevention plan. On January 8, 2025, SHPO agreed with the assessment that there are no known historic properties affected within the APE; on February 10, 2025, OAS agreed with findings concerning the absence of effects on prehistoric archaeological resources. These are qualified findings: if historic properties or resources are encountered during construction, the City must halt work in their vicinity and notify Reclamation; work may resume only after Reclamation completes SHPO consultation and any appropriate protective measures are implemented. The FONSI reports these determinations and requirements but does not establish the current status of every required permit or condition.

Attributed to US Bureau of Reclamation own-government project narrative.

Source: US Bureau of Reclamation screened government project narrative · publication date not recorded · observed 2026-10-02

Sources and evidence · US Bureau of Reclamation screened government project narrative
Source published: Not recordedObserved: 2026-10-02

US Bureau of Reclamation screened government project narrative
Attributed to US Bureau of Reclamation own-government project narrative

Technical record · Reclamation issued a FONSI, finding that the project …
Evidence location
page:7
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
a02f5fa3-2a67-44f0-821f-3e8008a4d758
Evidence reference
253b6b4c-6354-4081-add0-19be122688f3
Source revision
b47fa43f-1cc3-4f20-ae97-50c5c3d4d4ad
Content fingerprint
8560cc0966ca088fc39f9f825c207cbe105906b25b8d8e704fabcdb92c86b7f3
Source address
https://www.usbr.gov/gp/nepa/stigler_fonsi.pdf

Next milestone

Planned

The FONSI requires the City to obtain an OKR10 Construction Stormwater Permit before beginning construction. It does not establish whether the permit has since been obtained or give a construction start date.

Attributed to US Bureau of Reclamation own-government project narrative.

Source: US Bureau of Reclamation screened government project narrative · publication date not recorded · observed 2026-10-02

Sources and evidence · US Bureau of Reclamation screened government project narrative
Source published: Not recordedObserved: 2026-10-02

US Bureau of Reclamation screened government project narrative
Attributed to US Bureau of Reclamation own-government project narrative

Technical record · The FONSI requires the City to obtain an …
Evidence location
page:5
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
772171e4-76a0-452b-974a-2e8481f94f0c
Evidence reference
8437587c-0c48-4681-bbeb-ed90b4bf4a9e
Source revision
b47fa43f-1cc3-4f20-ae97-50c5c3d4d4ad
Content fingerprint
8560cc0966ca088fc39f9f825c207cbe105906b25b8d8e704fabcdb92c86b7f3
Source address
https://www.usbr.gov/gp/nepa/stigler_fonsi.pdf

Financing stage

Source reported

The City applied for and received a federal grant through Reclamation’s Drought Resiliency Program, and Reclamation says it is providing project funding. The source gives no grant amount, disbursement details, or total project cost.

Attributed to US Bureau of Reclamation own-government project narrative.

Source: US Bureau of Reclamation screened government project narrative · publication date not recorded · observed 2026-10-02

Sources and evidence · US Bureau of Reclamation screened government project narrative
Source published: Not recordedObserved: 2026-10-02

US Bureau of Reclamation screened government project narrative
Attributed to US Bureau of Reclamation own-government project narrative

Technical record · The City applied for and received a federal …
Evidence location
page:3
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
33830f2b-f54f-4a95-a84a-153298ff3a52
Evidence reference
3b55572e-f0b3-4a93-9ce0-b3155a9f8f3f
Source revision
b47fa43f-1cc3-4f20-ae97-50c5c3d4d4ad
Content fingerprint
8560cc0966ca088fc39f9f825c207cbe105906b25b8d8e704fabcdb92c86b7f3
Source address
https://www.usbr.gov/gp/nepa/stigler_fonsi.pdf
Source report history

Prior and superseded states remain labelled. Dates below identify source publication when known, otherwise source observation. They are not assumed event dates; each fact retains its own time qualifications.

  1. No material timeline events have been released.

Follow this project

Get project updates by email when new information is published.

Follow for free without an account, with the option to unsubscribe anytime. We'll email you a link to confirm.

DEEPRFP, S.L.U. uses your email and selected project to confirm and deliver the updates you request. You can stop anytime. Product news needs a separate opt-in. Read the Privacy Policy for legal bases, recipients, retention, your rights and contact details.