ZAC Grande Borne Ouest

France · Social infrastructure

In-depth research Release 1

Project scope

Plan: The 34-hectare zone includes the Places Hautes and Méridien sectors of Grande Borne, an area extending northeast to the Buffle–Autruche–Pégase school group and Amédée Gordini T12 tram stop, and a mixed housing-and-economic-activity strip between RD 445 and route de Fleury. Planned works include demolishing 414 residential units on the Places Hautes slab and building about 375 new homes, shops and activity space; demolishing the southeast gable of Grand Méridien and its ten homes to extend rue Toussaint Louverture; and remaking public spaces and streets. RD 445 is to be reconfigured as an urban boulevard with two traffic lanes in each direction, a central TZen 4 corridor, bidirectional cycle facilities and planted stormwater swales. The project also refers to rehabilitation of 480 Méridien homes, but the opinion says the dossier does not consistently or comprehensively include rehabilitation and residentialisation of retained buildings; those landlord-led operations are not fully described in the project impact assessment.

Reported status and procurement

Reported development

The opinion reports that demolition of the Place de l’Oiseau and Place de la Treille sub-sectors (187 homes) was planned for 2025–2026 and had begun; demolition of Place aux Herbes and Place du Quinconce (227 homes) was planned from 2028. These are report-date schedules, not confirmation of current progress.

Procurement availability
Unknown / not established

Reported regulatory context

The ZAC was created by prefectural order on 18 March 2024 after public consultation. An environmental authorization process, including review under water legislation, was still being examined when the environmental-authority opinion was issued.

A source report alone does not establish current progress or an open buying window.

Project summary

An environmental-authority opinion adopted on 25 September 2025 describes the ZAC Grande Borne Ouest, a 34-hectare urban renewal and mixed-use project in Grigny and Viry-Châtillon. Grand Paris Aménagement is identified as its development authority. The plan combines housing replacement, commercial and economic uses, public-space and street works, and transport-related infrastructure.

The opinion reports that the ZAC was created by prefectural order on 18 March 2024, while environmental authorization was still under examination when the opinion was issued. Its review also notes that the project dossier did not fully cover rehabilitation and residentialisation of retained buildings, and that several ecological design and monitoring details remained insufficiently specified.

Evidence limits and unknowns

The opinion does not establish the outcome or date of the environmental authorization; it reports that the process was still under examination when issued on 25 September 2025.

The final scope, schedule and assessed impacts of rehabilitation and residentialisation of retained homes remain unclear in the opinion; it notes incomplete project coverage and differing descriptions of rehabilitation.

The opinion identifies outstanding detail on planting choices, ecological functions and monitoring of proposed measures.

The demolition schedules in the opinion are report-date plans, not confirmation of current progress.

Is this project a fit for your company?

Check how this project relates to what your company supplies, with evidence gaps and a next step.

Create your account for free and include your business details to get custom commercial assessments.

Project metadata

Country
France
Based on reviewed release evidence
Region
Europe
Category
Social infrastructure
Derived from released evidence
Physical assets
Not classified

Based on this release's supporting evidence. Unresolved fields remain unclassified; these labels do not establish current progress or a buying window.

Released facts and supporting evidence

Each fact retains its source, uncertainty and time context. If a publisher page moves or is unavailable, use the recorded quotation and observation date below.

Project name

Source reported

ZAC Grande Borne Ouest

Attributed to IGEDD/Ae own dated environmental opinion with attributed project dossier facts.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-04

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-04

IGEDD environmental authority native opinion text
Attributed to IGEDD/Ae own dated environmental opinion with attributed project dossier facts

Technical record · ZAC Grande Borne Ouest
Evidence location
page:1
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
b88ef70b-69f6-437d-bf88-4b52f188a7c9
Evidence reference
4891c332-18ff-436c-88c1-240db3c9e8a7
Source revision
f162d2d9-8145-4a6f-8a1f-38f483dcc98a
Content fingerprint
4d64970b03b2b94a7cb9d401acc7084deb1020e882c9002cad194b29aa728b91
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/2_-_creation_de_la_zac_de_la_grande_borne_ouest_a_grigny_et_viry-chatillon_91__cle516f41-1.pdf

Scope

Planned

The 34-hectare zone includes the Places Hautes and Méridien sectors of Grande Borne, an area extending northeast to the Buffle–Autruche–Pégase school group and Amédée Gordini T12 tram stop, and a mixed housing-and-economic-activity strip between RD 445 and route de Fleury. Planned works include demolishing 414 residential units on the Places Hautes slab and building about 375 new homes, shops and activity space; demolishing the southeast gable of Grand Méridien and its ten homes to extend rue Toussaint Louverture; and remaking public spaces and streets. RD 445 is to be reconfigured as an urban boulevard with two traffic lanes in each direction, a central TZen 4 corridor, bidirectional cycle facilities and planted stormwater swales. The project also refers to rehabilitation of 480 Méridien homes, but the opinion says the dossier does not consistently or comprehensively include rehabilitation and residentialisation of retained buildings; those landlord-led operations are not fully described in the project impact assessment.

Attributed to IGEDD/Ae own dated environmental opinion with attributed project dossier facts.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-04

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-04

IGEDD environmental authority native opinion text
Attributed to IGEDD/Ae own dated environmental opinion with attributed project dossier facts

Technical record · The 34-hectare zone includes the Places Hautes and …
Evidence location
page:3
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
ac2452c5-da79-4c5f-8188-32a376a86293
Evidence reference
426c1ea8-cff0-4e5f-b494-ef2e9366198c
Source revision
f162d2d9-8145-4a6f-8a1f-38f483dcc98a
Content fingerprint
4d64970b03b2b94a7cb9d401acc7084deb1020e882c9002cad194b29aa728b91
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/2_-_creation_de_la_zac_de_la_grande_borne_ouest_a_grigny_et_viry-chatillon_91__cle516f41-1.pdf

Project ecology

Planned

The plan includes increased planting, permeable areas, planted swales and an intended ecological connection toward the Sapinière. The environmental authority says that planting choices, ecological functions and implementation and monitoring details remain insufficiently specified.

Attributed to IGEDD/Ae own dated environmental opinion with attributed project dossier facts.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-04

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-04

IGEDD environmental authority native opinion text
Attributed to IGEDD/Ae own dated environmental opinion with attributed project dossier facts

Technical record · The plan includes increased planting, permeable areas, planted …
Evidence location
page:7
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
b804b4dd-d604-4872-8347-1b4707771722
Evidence reference
17030cb8-c7b0-4ef5-ac56-cb45902c37ab
Source revision
f162d2d9-8145-4a6f-8a1f-38f483dcc98a
Content fingerprint
4d64970b03b2b94a7cb9d401acc7084deb1020e882c9002cad194b29aa728b91
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/2_-_creation_de_la_zac_de_la_grande_borne_ouest_a_grigny_et_viry-chatillon_91__cle516f41-1.pdf

Current activity

Planned

Urban renewal and mixed-use development, combining housing replacement, commercial and economic activities, street and public-space improvements, and transport-related infrastructure.

Attributed to IGEDD/Ae own dated environmental opinion with attributed project dossier facts.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-04

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-04

IGEDD environmental authority native opinion text
Attributed to IGEDD/Ae own dated environmental opinion with attributed project dossier facts

Technical record · Urban renewal and mixed-use development, combining housing replacement, …
Evidence location
page:3
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
919e7be2-b2c4-47ed-ba84-f517023c0ce5
Evidence reference
426c1ea8-cff0-4e5f-b494-ef2e9366198c
Source revision
f162d2d9-8145-4a6f-8a1f-38f483dcc98a
Content fingerprint
4d64970b03b2b94a7cb9d401acc7084deb1020e882c9002cad194b29aa728b91
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/2_-_creation_de_la_zac_de_la_grande_borne_ouest_a_grigny_et_viry-chatillon_91__cle516f41-1.pdf

Delivery

Source reported

The opinion reports that demolition of the Place de l’Oiseau and Place de la Treille sub-sectors (187 homes) was planned for 2025–2026 and had begun; demolition of Place aux Herbes and Place du Quinconce (227 homes) was planned from 2028. These are report-date schedules, not confirmation of current progress.

Attributed to IGEDD/Ae own dated environmental opinion with attributed project dossier facts.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-04

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-04

IGEDD environmental authority native opinion text
Attributed to IGEDD/Ae own dated environmental opinion with attributed project dossier facts

Technical record · The opinion reports that demolition of the Place …
Evidence location
page:6
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
0209bfa4-ed6c-48a8-8b21-839b23edf498
Evidence reference
3c184c65-983c-4c6d-93cb-7babf54c1480
Source revision
f162d2d9-8145-4a6f-8a1f-38f483dcc98a
Content fingerprint
4d64970b03b2b94a7cb9d401acc7084deb1020e882c9002cad194b29aa728b91
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/2_-_creation_de_la_zac_de_la_grande_borne_ouest_a_grigny_et_viry-chatillon_91__cle516f41-1.pdf

Location

Source reported

Grande Borne, in Grigny and Viry-Châtillon, Essonne (department 91), Île-de-France, France; the site is about 30 km south of Paris, beside the A6.

Attributed to IGEDD/Ae own dated environmental opinion with attributed project dossier facts.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-04

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-04

IGEDD environmental authority native opinion text
Attributed to IGEDD/Ae own dated environmental opinion with attributed project dossier facts

Technical record · Grande Borne, in Grigny and Viry-Châtillon, Essonne (department …
Evidence location
page:3
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
fbd48828-0ec4-408a-bc79-3cf7cf5ecff4
Evidence reference
426c1ea8-cff0-4e5f-b494-ef2e9366198c
Source revision
f162d2d9-8145-4a6f-8a1f-38f483dcc98a
Content fingerprint
4d64970b03b2b94a7cb9d401acc7084deb1020e882c9002cad194b29aa728b91
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/2_-_creation_de_la_zac_de_la_grande_borne_ouest_a_grigny_et_viry-chatillon_91__cle516f41-1.pdf

Regulatory evidence

Source reported

The ZAC was created by prefectural order on 18 March 2024 after public consultation. An environmental authorization process, including review under water legislation, was still being examined when the environmental-authority opinion was issued.

Attributed to IGEDD/Ae own dated environmental opinion with attributed project dossier facts.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-04

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-04

IGEDD environmental authority native opinion text
Attributed to IGEDD/Ae own dated environmental opinion with attributed project dossier facts

Technical record · The ZAC was created by prefectural order on …
Evidence location
page:8
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
d5b6c510-6cfd-4859-b319-561711bac282
Evidence reference
c1e64a3d-e4e3-4bed-a41d-5c2cc6ac4ccc
Source revision
f162d2d9-8145-4a6f-8a1f-38f483dcc98a
Content fingerprint
4d64970b03b2b94a7cb9d401acc7084deb1020e882c9002cad194b29aa728b91
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/2_-_creation_de_la_zac_de_la_grande_borne_ouest_a_grigny_et_viry-chatillon_91__cle516f41-1.pdf

Implementing agency

Source reported

Grand Paris Aménagement is identified as the aménageur (development authority) for the ZAC.

Attributed to IGEDD/Ae own dated environmental opinion with attributed project dossier facts.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-04

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-04

IGEDD environmental authority native opinion text
Attributed to IGEDD/Ae own dated environmental opinion with attributed project dossier facts

Technical record · Grand Paris Aménagement is identified as the aménageur …
Evidence location
page:5
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
48c04aea-c75f-4716-9141-cc81193c9b1a
Evidence reference
fa2b03b2-f850-4878-a799-3e06a1e2daff
Source revision
f162d2d9-8145-4a6f-8a1f-38f483dcc98a
Content fingerprint
4d64970b03b2b94a7cb9d401acc7084deb1020e882c9002cad194b29aa728b91
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/2_-_creation_de_la_zac_de_la_grande_borne_ouest_a_grigny_et_viry-chatillon_91__cle516f41-1.pdf
Source report history

Prior and superseded states remain labelled. Dates below identify source publication when known, otherwise source observation. They are not assumed event dates; each fact retains its own time qualifications.

  1. No material timeline events have been released.

Follow this project

Get project updates by email when new information is published.

Follow for free without an account, with the option to unsubscribe anytime. We'll email you a link to confirm.

DEEPRFP, S.L.U. uses your email and selected project to confirm and deliver the updates you request. You can stop anytime. Product news needs a separate opt-in. Read the Privacy Policy for legal bases, recipients, retention, your rights and contact details.