Skip to content
Menu
CapexCue · Public evidence · Printed 11 Nov 2026
Explore projects / Project dossier

Mouly hydroelectric plant

Name note: Also known as the Pont des Grottes plant.

France · Energy

In-depth research Release 1

Project scope

Plan: The existing run-of-river installation is described as having a roughly 415 m headrace canal, a Kaplan turbine in the existing powerhouse, a 16 m tailrace, and a weir; its reported baseline is 149 kW maximum gross power and about 780 MWh/year average generation over the preceding 18 years. The integrated proposal would widen and extend the headrace along its left bank, install a new turbine in a new powerhouse while retaining the existing building and recycling its equipment, replace the headgate, and rework the existing weir to add a fish pass and rebuild the boat passage. The new powerhouse is not to have a fish pass. About 11,300 m³ of excavated earth is to be made available to neighboring agricultural landowners. The proposed maximum turbine flow is 14 m³/s from November through May and 6.9 m³/s for the rest of the year; proposed maximum gross power is 597 kW. The opinion reports modeled annual generation of 2,423 MWh as the proponent’s more realistic estimate, while also noting a theoretical calculation of 2,610 MWh. The opinion says the currently authorized maximum diverted flow is 3.5 m³/s but that actual diversion is about 6.5 m³/s, reported in the file and confirmed during the exchange with the reviewers. It describes a current reserved flow of 10 m³/s.

Reported status and procurement

Reported development

Plan: The works were described during the reviewers’ site visit as planned in two phases of six months each, scheduled for low-water periods. The opinion says the file does not clearly or consistently explain the works, their duration or sequencing. Described operations include dewatering the headrace for construction of the new powerhouse, followed by staged dewatering at the weir to widen the canal, install gates and repair the intake, then construct the fish pass and boat passage.

Procurement availability
Unknown / not established

Reported regulatory context

The environmental authority issued its opinion on 25 September 2025 after receiving the file on 15 July 2025. The opinion is neither favorable nor unfavorable and is not the authorization decision. The project is subject to environmental assessment following case-by-case review; the proponent submitted an environmental impact study voluntarily, and the described environmental authorization application also covers water-law and electricity-generation authorizations. The project is subject to Natura 2000 impact assessment. The opinion says the existing installation had not completed all compliance works prescribed in 2003 and lacked a water operating regulation. It also notes an earlier environmental opinion in 2016 and references to a public inquiry initially planned for 2017, whose status required clarification following regulatory changes. The supplied material does not establish whether the current application has since been authorized or whether a public inquiry has occurred.

A source report alone does not establish current progress or an open buying window.

Project summary

The Mouly hydroelectric plant, also called the Pont des Grottes plant, is an existing run-of-river facility on the Gave de Pau at Lestelle-Bétharram and Saint-Pé-de-Bigorre. SARL de Lauture is identified as its operator and project proponent. The proposal would expand the headrace, add a new powerhouse and turbine, and rework the weir to provide fish and boat passages. Proposed maximum gross power is 597 kW; the opinion reports 2,423 MWh/year as the proponent’s more realistic modeled generation estimate, distinct from a theoretical 2,610 MWh calculation.

The environmental authority’s opinion, dated 25 September 2025, raises concerns about ecological continuity, habitats, climate-related flows and sharing water with whitewater recreation. It calls for stronger analysis of hydrology and impacts. The opinion is neither favorable nor unfavorable and is not an authorization decision.

Evidence limits and unknowns

Whether the environmental authorization or other required permits were granted after the 25 September 2025 opinion, and whether public participation subsequently took place.

Construction start dates and the final confirmed works schedule. The opinion describes two planned six-month phases during low-water periods but says the file does not clearly explain the works, duration or sequencing.

Final detailed drawings and exact boundaries of excavation, infill, canal widening and work around the existing powerhouse; the opinion says these descriptions were incomplete.

The final operating and reserved-flow regime, including how it will address future hydrological conditions and balance ecological needs, electricity generation and water sports.

Project financing, named contractors, procurement arrangements and the identity of the electricity purchaser are not established in the supplied extracts.

The supplied text covers pages 2–12 and 27–28 of the 28-page opinion; pages 13–26 and graphical content were not interpreted.

Is this project a fit for your company?

Check how this project relates to what your company supplies, with evidence gaps and a next step.

Create your account for free and include your business details to get custom commercial assessments.

Project metadata

Country
France
Based on reviewed release evidence
Region
Europe
Category
Energy
Derived from released evidence
Physical assets
Hydropower

Based on this release's supporting evidence. Unresolved fields remain unclassified; these labels do not establish current progress or a buying window.

Released facts and supporting evidence

Each fact retains its source, uncertainty and time context. If a publisher page moves or is unavailable, use the recorded quotation and observation date below.

Project name

Source reported

Mouly hydroelectric plant, also known as the Pont des Grottes plant.

Attributed to IGEDD Autorité environnementale opinion: authority synthesis and attributed developer facts.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-03

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-03

IGEDD environmental authority native opinion text
Attributed to IGEDD Autorité environnementale opinion: authority synthesis and attributed developer facts

Technical record · Mouly hydroelectric plant, also known as the Pont …
Evidence location
page:3
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
e1ca3102-6bd3-48de-a4d7-b1d7ac4422a4
Evidence reference
0e1bfc0a-a1ca-4577-96a7-07cdc05d8688
Source revision
aa0ebe98-a8b1-4dd3-b2d7-c69c9324a6af
Content fingerprint
0d134cd5708ff0c0c8ad4fbad2824bf34697f51e284bc0236daac0c5b9807818
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/3_-_centrale_hydroelectrique_du_mouly_sur_le_gave_de_pau_cle1f9fef.pdf

Scope

Planned

The existing run-of-river installation is described as having a roughly 415 m headrace canal, a Kaplan turbine in the existing powerhouse, a 16 m tailrace, and a weir; its reported baseline is 149 kW maximum gross power and about 780 MWh/year average generation over the preceding 18 years. The integrated proposal would widen and extend the headrace along its left bank, install a new turbine in a new powerhouse while retaining the existing building and recycling its equipment, replace the headgate, and rework the existing weir to add a fish pass and rebuild the boat passage. The new powerhouse is not to have a fish pass. About 11,300 m³ of excavated earth is to be made available to neighboring agricultural landowners. The proposed maximum turbine flow is 14 m³/s from November through May and 6.9 m³/s for the rest of the year; proposed maximum gross power is 597 kW. The opinion reports modeled annual generation of 2,423 MWh as the proponent’s more realistic estimate, while also noting a theoretical calculation of 2,610 MWh. The opinion says the currently authorized maximum diverted flow is 3.5 m³/s but that actual diversion is about 6.5 m³/s, reported in the file and confirmed during the exchange with the reviewers. It describes a current reserved flow of 10 m³/s.

Attributed to IGEDD Autorité environnementale opinion: authority synthesis and attributed developer facts.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-03

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-03

IGEDD environmental authority native opinion text
Attributed to IGEDD Autorité environnementale opinion: authority synthesis and attributed developer facts

Technical record · The existing run-of-river installation is described as having …
Evidence location
page:3
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
5451beee-01a6-44ba-a9d7-b6a0104f4913
Evidence reference
0e1bfc0a-a1ca-4577-96a7-07cdc05d8688
Source revision
aa0ebe98-a8b1-4dd3-b2d7-c69c9324a6af
Content fingerprint
0d134cd5708ff0c0c8ad4fbad2824bf34697f51e284bc0236daac0c5b9807818
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/3_-_centrale_hydroelectrique_du_mouly_sur_le_gave_de_pau_cle1f9fef.pdf

Country

Source reported

France

Attributed to IGEDD Autorité environnementale opinion: authority synthesis and attributed developer facts.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-03

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-03

IGEDD environmental authority native opinion text
Attributed to IGEDD Autorité environnementale opinion: authority synthesis and attributed developer facts

Technical record · France
Evidence location
page:4
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
4933f17d-9989-4282-aa20-6a6f78b50a9a
Evidence reference
d1d200f5-1c26-45d6-b9d7-d7bbe9c2f2b6
Source revision
aa0ebe98-a8b1-4dd3-b2d7-c69c9324a6af
Content fingerprint
0d134cd5708ff0c0c8ad4fbad2824bf34697f51e284bc0236daac0c5b9807818
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/3_-_centrale_hydroelectrique_du_mouly_sur_le_gave_de_pau_cle1f9fef.pdf

Project ecology

Source reported

The opinion identifies ecological continuity, aquatic and alluvial habitats, water quality, climate-related changes to flows, and sharing water with whitewater recreation as important issues. It identifies the Atlantic salmon, European otter and Pyrenean desman among relevant species; the existing structures are described as preventing fish passage, and the proposed fish pass is intended to address this. The opinion raises concerns that the assessment does not adequately establish how the project will protect habitats and reconcile water uses under changing flows, and calls for better baseline and impact analysis. It also reports a sharp decline in observed salmon reproduction in 2024 and a fishing prohibition effective from July 2024. A monitoring program is described, including flow monitoring, fish surveys and reporting, but the opinion notes that monitoring frequencies, alert thresholds, responsibilities, resources and reporting arrangements are not adequately specified.

Attributed to IGEDD Autorité environnementale opinion: authority synthesis and attributed developer facts.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-03

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-03

IGEDD environmental authority native opinion text
Attributed to IGEDD Autorité environnementale opinion: authority synthesis and attributed developer facts

Technical record · The opinion identifies ecological continuity, aquatic and alluvial …
Evidence location
page:3
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
87813afd-40f5-4103-ac8d-a6054bf14f10
Evidence reference
0e1bfc0a-a1ca-4577-96a7-07cdc05d8688
Source revision
aa0ebe98-a8b1-4dd3-b2d7-c69c9324a6af
Content fingerprint
0d134cd5708ff0c0c8ad4fbad2824bf34697f51e284bc0236daac0c5b9807818
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/3_-_centrale_hydroelectrique_du_mouly_sur_le_gave_de_pau_cle1f9fef.pdf

Current activity

Source reported

The existing facility generates hydroelectricity. The same river reach is also used for whitewater recreation and training, including slalom and freestyle kayaking; the opinion describes the site as a rare natural kayaking site in France and notes international-level practice on this stretch.

Attributed to IGEDD Autorité environnementale opinion: authority synthesis and attributed developer facts.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-03

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-03

IGEDD environmental authority native opinion text
Attributed to IGEDD Autorité environnementale opinion: authority synthesis and attributed developer facts

Technical record · The existing facility generates hydroelectricity. The same river …
Evidence location
page:3
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
b7d10999-6a41-41d4-a01f-7a7ca9d75763
Evidence reference
0e1bfc0a-a1ca-4577-96a7-07cdc05d8688
Source revision
aa0ebe98-a8b1-4dd3-b2d7-c69c9324a6af
Content fingerprint
0d134cd5708ff0c0c8ad4fbad2824bf34697f51e284bc0236daac0c5b9807818
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/3_-_centrale_hydroelectrique_du_mouly_sur_le_gave_de_pau_cle1f9fef.pdf

Delivery

Planned

The works were described during the reviewers’ site visit as planned in two phases of six months each, scheduled for low-water periods. The opinion says the file does not clearly or consistently explain the works, their duration or sequencing. Described operations include dewatering the headrace for construction of the new powerhouse, followed by staged dewatering at the weir to widen the canal, install gates and repair the intake, then construct the fish pass and boat passage.

Attributed to IGEDD Autorité environnementale opinion: authority synthesis and attributed developer facts.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-03

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-03

IGEDD environmental authority native opinion text
Attributed to IGEDD Autorité environnementale opinion: authority synthesis and attributed developer facts

Technical record · The works were described during the reviewers’ site …
Evidence location
page:8
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
77baa998-b356-4187-830f-9ebca3a7218e
Evidence reference
56dedf85-a6f7-43a9-9367-58d5e952f0ac
Source revision
aa0ebe98-a8b1-4dd3-b2d7-c69c9324a6af
Content fingerprint
0d134cd5708ff0c0c8ad4fbad2824bf34697f51e284bc0236daac0c5b9807818
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/3_-_centrale_hydroelectrique_du_mouly_sur_le_gave_de_pau_cle1f9fef.pdf

Location

Source reported

On the Gave de Pau, across Lestelle-Bétharram in Pyrénées-Atlantiques (department 64) and Saint-Pé-de-Bigorre in Hautes-Pyrénées (department 65), spanning Nouvelle-Aquitaine and Occitanie. The opinion notes administrative complexity, including differing status of the banks.

Attributed to IGEDD Autorité environnementale opinion: authority synthesis and attributed developer facts.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-03

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-03

IGEDD environmental authority native opinion text
Attributed to IGEDD Autorité environnementale opinion: authority synthesis and attributed developer facts

Technical record · On the Gave de Pau, across Lestelle-Bétharram in …
Evidence location
page:3
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
a98bbdef-1e08-4b5b-86a4-1c299fdee035
Evidence reference
0e1bfc0a-a1ca-4577-96a7-07cdc05d8688
Source revision
aa0ebe98-a8b1-4dd3-b2d7-c69c9324a6af
Content fingerprint
0d134cd5708ff0c0c8ad4fbad2824bf34697f51e284bc0236daac0c5b9807818
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/3_-_centrale_hydroelectrique_du_mouly_sur_le_gave_de_pau_cle1f9fef.pdf

Developer

Source reported

SARL de Lauture is identified as the current operator and as the project petitioner/proponent.

Attributed to IGEDD Autorité environnementale opinion: authority synthesis and attributed developer facts.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-03

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-03

IGEDD environmental authority native opinion text
Attributed to IGEDD Autorité environnementale opinion: authority synthesis and attributed developer facts

Technical record · SARL de Lauture is identified as the current …
Evidence location
page:3
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
786cd2c2-00c8-4cfc-accb-54009be61508
Evidence reference
0e1bfc0a-a1ca-4577-96a7-07cdc05d8688
Source revision
aa0ebe98-a8b1-4dd3-b2d7-c69c9324a6af
Content fingerprint
0d134cd5708ff0c0c8ad4fbad2824bf34697f51e284bc0236daac0c5b9807818
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/3_-_centrale_hydroelectrique_du_mouly_sur_le_gave_de_pau_cle1f9fef.pdf

Regulatory evidence

Source reported

The environmental authority issued its opinion on 25 September 2025 after receiving the file on 15 July 2025. The opinion is neither favorable nor unfavorable and is not the authorization decision. The project is subject to environmental assessment following case-by-case review; the proponent submitted an environmental impact study voluntarily, and the described environmental authorization application also covers water-law and electricity-generation authorizations. The project is subject to Natura 2000 impact assessment. The opinion says the existing installation had not completed all compliance works prescribed in 2003 and lacked a water operating regulation. It also notes an earlier environmental opinion in 2016 and references to a public inquiry initially planned for 2017, whose status required clarification following regulatory changes. The supplied material does not establish whether the current application has since been authorized or whether a public inquiry has occurred.

Attributed to IGEDD Autorité environnementale opinion: authority synthesis and attributed developer facts.

Source: IGEDD environmental authority native opinion text · publication date not recorded · observed 2026-10-03

Sources and evidence · IGEDD environmental authority native opinion text
Source published: Not recordedObserved: 2026-10-03

IGEDD environmental authority native opinion text
Attributed to IGEDD Autorité environnementale opinion: authority synthesis and attributed developer facts

Technical record · The environmental authority issued its opinion on 25 …
Evidence location
page:2
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
6904d45a-80ce-468a-af18-ce7f35f08a7f
Evidence reference
9790b237-8b27-481d-a5a2-986a7ae2beeb
Source revision
aa0ebe98-a8b1-4dd3-b2d7-c69c9324a6af
Content fingerprint
0d134cd5708ff0c0c8ad4fbad2824bf34697f51e284bc0236daac0c5b9807818
Source address
https://www.igedd.developpement-durable.gouv.fr/IMG/pdf/3_-_centrale_hydroelectrique_du_mouly_sur_le_gave_de_pau_cle1f9fef.pdf
Source report history

Prior and superseded states remain labelled. Dates below identify source publication when known, otherwise source observation. They are not assumed event dates; each fact retains its own time qualifications.

  1. No material timeline events have been released.

Follow this project

Get project updates by email when new information is published.

Follow for free without an account, with the option to unsubscribe anytime. We'll email you a link to confirm.

DEEPRFP, S.L.U. uses your email and selected project to confirm and deliver the updates you request. You can stop anytime. Product news needs a separate opt-in. Read the Privacy Policy for legal bases, recipients, retention, your rights and contact details.