Summerfield Battery Energy Storage System (Summerfield BESS).

Australia · Energy

In-depth research Release 1

Project scope

Battery energy storage system rated at 240 MWac / 960 MWh.

Reported status and procurement

Reported development

Construction commenced in February 2025.

Procurement availability
Unknown / not established

A source report alone does not establish current progress or an open buying window.

Project summary

Summerfield BESS is a 240 MWac / 960 MWh battery energy storage project approximately 50 km east of Adelaide, South Australia. Construction commenced in February 2025. The announcement dated 13 April 2026 reports that Palisade had agreed to acquire a 100% interest from CIP through Intera, but does not report completion. It describes the project as partway through construction, while a quoted CIP statement says construction was substantially complete. Commercial operations were scheduled for late 2026.

Evidence limits and unknowns

The supplied announcement, dated 13 April 2026, does not establish whether the acquisition subsequently closed or provide a later construction or operations update. It does not state procurement or tender status, project budget, EPC, or equipment suppliers.

Is this project a fit for your company?

Check how this project relates to what your company supplies, with evidence gaps and a next step.

Create your account for free and include your business details to get custom commercial assessments.

Project metadata

Country
Australia
Based on reviewed release evidence
Region
Oceania
Category
Energy
Derived from released evidence
Physical assets
Battery Storage

Based on this release's supporting evidence. Unresolved fields remain unclassified; these labels do not establish current progress or a buying window.

Released facts and supporting evidence

Each fact retains its source, uncertainty and time context. If a publisher page moves or is unavailable, use the recorded quotation and observation date below.

Date

Source reported

The announcement is dated 13 April 2026.

Attributed to www.palisadegroup.com.

Source: www.palisadegroup.com · publication date not recorded · observed 2026-10-17

Sources and evidence · www.palisadegroup.com
Source published: Not recordedObserved: 2026-10-17

www.palisadegroup.com
Attributed to www.palisadegroup.com

Technical record · The announcement is dated 13 April 2026.
Evidence location
/html/body/div/main/div[2]/div/article/div/div[1]/text-position:9
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
8d340ae2-3e3a-447d-be04-7d18e15ffac9
Evidence reference
5defba1c-a93c-47e4-af73-72f173665191
Source revision
8a7c635b-e5e6-4255-b7d0-a330be9c4207
Content fingerprint
b64e7154292b3c9e2928aac341d351221189ece4dd063f81a4e853d617ffec68
Source address
https://www.palisadegroup.com/palisade-signs-transaction-to-acquire-second-large-scale-battery-through-intera-renewables/

Project name

Source reported

Summerfield Battery Energy Storage System (Summerfield BESS).

Attributed to www.palisadegroup.com.

Source: www.palisadegroup.com · publication date not recorded · observed 2026-10-17

Sources and evidence · www.palisadegroup.com
Source published: Not recordedObserved: 2026-10-17

www.palisadegroup.com
Attributed to www.palisadegroup.com

Technical record · Summerfield Battery Energy Storage System (Summerfield BESS).
Evidence location
/html/body/div/main/div[2]/div/article/div/p[1]
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
c2bc2bea-abee-4979-ad31-5707cb94caf8
Evidence reference
b9bf4f11-a9fa-48c0-810a-014145292fd7
Source revision
8a7c635b-e5e6-4255-b7d0-a330be9c4207
Content fingerprint
b64e7154292b3c9e2928aac341d351221189ece4dd063f81a4e853d617ffec68
Source address
https://www.palisadegroup.com/palisade-signs-transaction-to-acquire-second-large-scale-battery-through-intera-renewables/

Owner

Planned

Palisade Investment Partners reached an agreement to acquire a 100% interest from CIP through Intera Renewables; the article does not report that the acquisition was completed.

Attributed to www.palisadegroup.com.

Source: www.palisadegroup.com · publication date not recorded · observed 2026-10-17

Sources and evidence · www.palisadegroup.com
Source published: Not recordedObserved: 2026-10-17

www.palisadegroup.com
Attributed to www.palisadegroup.com

Technical record · Palisade Investment Partners reached an agreement to acquire …
Evidence location
/html/body/div/main/div[2]/div/article/div/div[1]/text-position:9
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
fbfc36c4-2afb-487b-a016-2e70bdc6c0e7
Evidence reference
5defba1c-a93c-47e4-af73-72f173665191
Source revision
8a7c635b-e5e6-4255-b7d0-a330be9c4207
Content fingerprint
b64e7154292b3c9e2928aac341d351221189ece4dd063f81a4e853d617ffec68
Source address
https://www.palisadegroup.com/palisade-signs-transaction-to-acquire-second-large-scale-battery-through-intera-renewables/

Scope

Source reported

Battery energy storage system rated at 240 MWac / 960 MWh.

Attributed to www.palisadegroup.com.

Source: www.palisadegroup.com · publication date not recorded · observed 2026-10-17

Sources and evidence · www.palisadegroup.com
Source published: Not recordedObserved: 2026-10-17

www.palisadegroup.com
Attributed to www.palisadegroup.com

Technical record · Battery energy storage system rated at 240 MWac …
Evidence location
/html/body/div/main/div[2]/div/article/div/p[2]
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
ed5a2ccb-0c2f-4718-853e-397a131729ca
Evidence reference
55de4d6d-d111-4965-be5e-8c78677b500b
Source revision
8a7c635b-e5e6-4255-b7d0-a330be9c4207
Content fingerprint
b64e7154292b3c9e2928aac341d351221189ece4dd063f81a4e853d617ffec68
Source address
https://www.palisadegroup.com/palisade-signs-transaction-to-acquire-second-large-scale-battery-through-intera-renewables/

Sector

Source reported

Energy storage.

Attributed to www.palisadegroup.com.

Source: www.palisadegroup.com · publication date not recorded · observed 2026-10-17

Sources and evidence · www.palisadegroup.com
Source published: Not recordedObserved: 2026-10-17

www.palisadegroup.com
Attributed to www.palisadegroup.com

Technical record · Energy storage.
Evidence location
/html/body/div/main/div[2]/div/article/div/p[2]
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
05523636-d6bf-4218-90ac-1aed450e4b0d
Evidence reference
55de4d6d-d111-4965-be5e-8c78677b500b
Source revision
8a7c635b-e5e6-4255-b7d0-a330be9c4207
Content fingerprint
b64e7154292b3c9e2928aac341d351221189ece4dd063f81a4e853d617ffec68
Source address
https://www.palisadegroup.com/palisade-signs-transaction-to-acquire-second-large-scale-battery-through-intera-renewables/

Current activity

Reported as actual

Construction commenced in February 2025.

Attributed to www.palisadegroup.com.

Source: www.palisadegroup.com · publication date not recorded · observed 2026-10-17

Sources and evidence · www.palisadegroup.com
Source published: Not recordedObserved: 2026-10-17

www.palisadegroup.com
Attributed to www.palisadegroup.com

Technical record · Construction commenced in February 2025.
Evidence location
/html/body/div/main/div[2]/div/article/div/p[2]
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
aa8a074e-8e04-4a39-861f-f7319e587669
Evidence reference
55de4d6d-d111-4965-be5e-8c78677b500b
Source revision
8a7c635b-e5e6-4255-b7d0-a330be9c4207
Content fingerprint
b64e7154292b3c9e2928aac341d351221189ece4dd063f81a4e853d617ffec68
Source address
https://www.palisadegroup.com/palisade-signs-transaction-to-acquire-second-large-scale-battery-through-intera-renewables/

Location

Source reported

Approximately 50 km east of Adelaide, South Australia, Australia.

Attributed to www.palisadegroup.com.

Source: www.palisadegroup.com · publication date not recorded · observed 2026-10-17

Sources and evidence · www.palisadegroup.com
Source published: Not recordedObserved: 2026-10-17

www.palisadegroup.com
Attributed to www.palisadegroup.com

Technical record · Approximately 50 km east of Adelaide, South Australia, …
Evidence location
/html/body/div/main/div[2]/div/article/div/p[2]
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
c72050b8-2c79-46dc-af45-42c56bb9a725
Evidence reference
55de4d6d-d111-4965-be5e-8c78677b500b
Source revision
8a7c635b-e5e6-4255-b7d0-a330be9c4207
Content fingerprint
b64e7154292b3c9e2928aac341d351221189ece4dd063f81a4e853d617ffec68
Source address
https://www.palisadegroup.com/palisade-signs-transaction-to-acquire-second-large-scale-battery-through-intera-renewables/

Developer

Source reported

Copenhagen Infrastructure Partners (CIP) developed the project.

Attributed to www.palisadegroup.com.

Source: www.palisadegroup.com · publication date not recorded · observed 2026-10-17

Sources and evidence · www.palisadegroup.com
Source published: Not recordedObserved: 2026-10-17

www.palisadegroup.com
Attributed to www.palisadegroup.com

Technical record · Copenhagen Infrastructure Partners (CIP) developed the project.
Evidence location
/html/body/div/main/div[2]/div/article/div/p[2]
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
c88cda56-b32c-4210-8fd7-ef6b56666e83
Evidence reference
55de4d6d-d111-4965-be5e-8c78677b500b
Source revision
8a7c635b-e5e6-4255-b7d0-a330be9c4207
Content fingerprint
b64e7154292b3c9e2928aac341d351221189ece4dd063f81a4e853d617ffec68
Source address
https://www.palisadegroup.com/palisade-signs-transaction-to-acquire-second-large-scale-battery-through-intera-renewables/

Next milestone

Planned

Commercial operations were scheduled to commence in late 2026.

Attributed to www.palisadegroup.com.

Source: www.palisadegroup.com · publication date not recorded · observed 2026-10-17

Sources and evidence · www.palisadegroup.com
Source published: Not recordedObserved: 2026-10-17

www.palisadegroup.com
Attributed to www.palisadegroup.com

Technical record · Commercial operations were scheduled to commence in late …
Evidence location
/html/body/div/main/div[2]/div/article/div/p[2]
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
e9e414d0-df0d-4910-a128-8a06819b4f34
Evidence reference
55de4d6d-d111-4965-be5e-8c78677b500b
Source revision
8a7c635b-e5e6-4255-b7d0-a330be9c4207
Content fingerprint
b64e7154292b3c9e2928aac341d351221189ece4dd063f81a4e853d617ffec68
Source address
https://www.palisadegroup.com/palisade-signs-transaction-to-acquire-second-large-scale-battery-through-intera-renewables/
Source report history

Prior and superseded states remain labelled. Dates below identify source publication when known, otherwise source observation. They are not assumed event dates; each fact retains its own time qualifications.

  1. No material timeline events have been released.

Follow this project

Get project updates by email when new information is published.

Follow for free without an account, with the option to unsubscribe anytime. We'll email you a link to confirm.

DEEPRFP, S.L.U. uses your email and selected project to confirm and deliver the updates you request. You can stop anytime. Product news needs a separate opt-in. Read the Privacy Policy for legal bases, recipients, retention, your rights and contact details.