Blackstone Battery Energy Storage System (BESS) Project

Australia · Energy

In-depth research Release 1

Project scope

Proposed 500 MW / 2,000 MWh standalone battery energy storage facility, with an approximately 7.25 ha project and disturbance footprint. Associated planned works include a new 275 kV substation, 275 kV underground cables to the existing Blackstone Substation, access roads, stormwater infrastructure, an operations and maintenance building, battery and electrical equipment, a temporary concrete batching plant, and mine remediation associated with historical underground tunnels in the eastern portion of the site.

Reported status and procurement

Reported development
Not established
Procurement availability
Unknown / not established

Reported procurement

Plan: Execution of the EPC and Long-Term Service Agreement (LTSA), and execution of connection and access agreements with Powerlink Queensland for the Blackstone Substation extension and high-voltage underground cables, are listed as future steps. The description does not state that these agreements have been executed.

Reported regulatory context

The portal displays project status “Referral Decision Made,” while the project description lists finalising Operational Works approvals with Ipswich City Council as a future step; neither establishes that all approvals are complete. The captured page states it is an offline, read-only version and warns that project status fields for some projects may update. The related-decisions table shows loading, permission and error messages and provides no usable decision details.

Reported financing

Plan: Completing project financing and achieving financial close are listed as steps to be completed following the EPBC Act referral.

A source report alone does not establish current progress or an open buying window.

Project summary

The referral describes a proposed 500 MW / 2,000 MWh standalone battery storage project at 45 Patrick Street, Swanbank, Queensland, with an approximately 7.25 ha footprint and associated substation, underground cables, site infrastructure, batching plant and mine-remediation works. Approximately 3.26 ha of mapped koala habitat is within the footprint; 2026 surveys identified habitat resources but directly observed no koalas.

Construction is expected to run from November 2026 to Q1 2029. The portal displays “Referral Decision Made,” but the captured page is offline/read-only, warns that some status fields may update, and provides no usable details in its related-decisions table. The description lists approvals, financing, EPC/LTSA execution and Powerlink agreements as future steps; it does not document an open procurement opportunity.

Evidence limits and unknowns

The portal capture was observed on 2026-10-17; the source provides no publication date. Current project status after that capture is not established.

The source does not establish whether financing, approvals, agreements or the Q4 2026 milestone have since been completed.

The project description does not state a budget or financing amount.

The related-decisions table provides no usable decision details.

Is this project a fit for your company?

Check how this project relates to what your company supplies, with evidence gaps and a next step.

Create your account for free and include your business details to get custom commercial assessments.

Project metadata

Country
Australia
Based on reviewed release evidence
Region
Oceania
Category
Energy
Derived from released evidence
Physical assets
Battery Storage, Electricity Transmission

Based on this release's supporting evidence. Unresolved fields remain unclassified; these labels do not establish current progress or a buying window.

Released facts and supporting evidence

Each fact retains its source, uncertainty and time context. If a publisher page moves or is unavailable, use the recorded quotation and observation date below.

Date

Planned

Construction is expected to start in November 2026 and finish in Q1 2029; operation is expected to start in Q1 2029 and continue until Q1 2054 (approximately 25 years); decommissioning is anticipated to commence in Q2 2054.

Attributed to epbcpublicportal.environment.gov.au.

Source: epbcpublicportal.environment.gov.au · publication date not recorded · observed 2026-10-17

Sources and evidence · epbcpublicportal.environment.gov.au
Source published: Not recordedObserved: 2026-10-17

epbcpublicportal.environment.gov.au
Attributed to epbcpublicportal.environment.gov.au

Technical record · Construction is expected to start in November 2026 …
Evidence location
/html/body/form/div[2]/div[2]/div/div/div/div[2]/div[2]/div[2]/div[1]/div/div/div[1]/div/div/div/fieldset[2]/table
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
86f15a39-593c-42fb-86e3-ea753cfbec44
Evidence reference
a1a6febe-d9f3-417e-a600-43a5ed522e28
Source revision
a1336c35-9dec-4d76-83c6-55bce60a23f4
Content fingerprint
0440f5b10c0f60df7b5fcb98d7a735048b83b2dc060820fb65c519f9060d814f
Source address
https://epbcpublicportal.environment.gov.au/all-referrals/project-referral-summary/?id=b82ae61b-219d-f111-b8db-6045bde6a109

Project name

Source reported

Blackstone Battery Energy Storage System (BESS) Project.

Attributed to epbcpublicportal.environment.gov.au.

Source: epbcpublicportal.environment.gov.au · publication date not recorded · observed 2026-10-17

Sources and evidence · epbcpublicportal.environment.gov.au
Source published: Not recordedObserved: 2026-10-17

epbcpublicportal.environment.gov.au
Attributed to epbcpublicportal.environment.gov.au

Technical record · Blackstone Battery Energy Storage System (BESS) Project.
Evidence location
/html/body/form/div[2]/div[2]/div/div/div/div[1]/div[1]/div/text-position:141
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
5d976a41-0d89-4801-9f28-1bea254d3a6f
Evidence reference
eb123aae-e488-4166-a862-082fb7258fc6
Source revision
a1336c35-9dec-4d76-83c6-55bce60a23f4
Content fingerprint
0440f5b10c0f60df7b5fcb98d7a735048b83b2dc060820fb65c519f9060d814f
Source address
https://epbcpublicportal.environment.gov.au/all-referrals/project-referral-summary/?id=b82ae61b-219d-f111-b8db-6045bde6a109

Scope

Planned

Proposed 500 MW / 2,000 MWh standalone battery energy storage facility, with an approximately 7.25 ha project and disturbance footprint. Associated planned works include a new 275 kV substation, 275 kV underground cables to the existing Blackstone Substation, access roads, stormwater infrastructure, an operations and maintenance building, battery and electrical equipment, a temporary concrete batching plant, and mine remediation associated with historical underground tunnels in the eastern portion of the site.

Attributed to epbcpublicportal.environment.gov.au.

Source: epbcpublicportal.environment.gov.au · publication date not recorded · observed 2026-10-17

Sources and evidence · epbcpublicportal.environment.gov.au
Source published: Not recordedObserved: 2026-10-17

epbcpublicportal.environment.gov.au
Attributed to epbcpublicportal.environment.gov.au

Technical record · Proposed 500 MW / 2,000 MWh standalone battery …
Evidence location
/html/body/form/div[2]/div[2]/div/div/div/div[2]/div[2]/div[2]/div[1]/div/div/div[1]/div/div/div/fieldset[2]/table
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
8d14838e-e77d-4285-95eb-177cd8562726
Evidence reference
a1a6febe-d9f3-417e-a600-43a5ed522e28
Source revision
a1336c35-9dec-4d76-83c6-55bce60a23f4
Content fingerprint
0440f5b10c0f60df7b5fcb98d7a735048b83b2dc060820fb65c519f9060d814f
Source address
https://epbcpublicportal.environment.gov.au/all-referrals/project-referral-summary/?id=b82ae61b-219d-f111-b8db-6045bde6a109

Project ecology

Source reported

Approximately 3.26 ha of mapped koala habitat is within the project footprint. Field surveys completed in 2026 identified koala habitat resources, but no koalas were directly observed.

Attributed to epbcpublicportal.environment.gov.au.

Source: epbcpublicportal.environment.gov.au · publication date not recorded · observed 2026-10-17

Sources and evidence · epbcpublicportal.environment.gov.au
Source published: Not recordedObserved: 2026-10-17

epbcpublicportal.environment.gov.au
Attributed to epbcpublicportal.environment.gov.au

Technical record · Approximately 3.26 ha of mapped koala habitat is …
Evidence location
/html/body/form/div[2]/div[2]/div/div/div/div[2]/div[2]/div[2]/div[1]/div/div/div[1]/div/div/div/fieldset[2]/table
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
aa6c7c3f-ac9e-4084-8ead-22d172b78b73
Evidence reference
a1a6febe-d9f3-417e-a600-43a5ed522e28
Source revision
a1336c35-9dec-4d76-83c6-55bce60a23f4
Content fingerprint
0440f5b10c0f60df7b5fcb98d7a735048b83b2dc060820fb65c519f9060d814f
Source address
https://epbcpublicportal.environment.gov.au/all-referrals/project-referral-summary/?id=b82ae61b-219d-f111-b8db-6045bde6a109

Location

Source reported

45 Patrick Street, Swanbank, Queensland, in the Swanbank–New Chum industrial precinct, adjacent to the existing Blackstone 275 kV Substation.

Attributed to epbcpublicportal.environment.gov.au.

Source: epbcpublicportal.environment.gov.au · publication date not recorded · observed 2026-10-17

Sources and evidence · epbcpublicportal.environment.gov.au
Source published: Not recordedObserved: 2026-10-17

epbcpublicportal.environment.gov.au
Attributed to epbcpublicportal.environment.gov.au

Technical record · 45 Patrick Street, Swanbank, Queensland, in the Swanbank–New …
Evidence location
/html/body/form/div[2]/div[2]/div/div/div/div[2]/div[2]/div[2]/div[1]/div/div/div[1]/div/div/div/fieldset[2]/table
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
09ee8d0f-21ce-42e9-aed9-eb86504d68dc
Evidence reference
a1a6febe-d9f3-417e-a600-43a5ed522e28
Source revision
a1336c35-9dec-4d76-83c6-55bce60a23f4
Content fingerprint
0440f5b10c0f60df7b5fcb98d7a735048b83b2dc060820fb65c519f9060d814f
Source address
https://epbcpublicportal.environment.gov.au/all-referrals/project-referral-summary/?id=b82ae61b-219d-f111-b8db-6045bde6a109

Contractor

Planned

Tesla is identified as the planned counterparty for the EPC and LTSA; execution is listed as a future step.

Attributed to epbcpublicportal.environment.gov.au.

Source: epbcpublicportal.environment.gov.au · publication date not recorded · observed 2026-10-17

Sources and evidence · epbcpublicportal.environment.gov.au
Source published: Not recordedObserved: 2026-10-17

epbcpublicportal.environment.gov.au
Attributed to epbcpublicportal.environment.gov.au

Technical record · Tesla is identified as the planned counterparty for …
Evidence location
/html/body/form/div[2]/div[2]/div/div/div/div[2]/div[2]/div[2]/div[1]/div/div/div[1]/div/div/div/fieldset[2]/table
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
8e0172a3-165d-4544-be7a-cee8dd0642c9
Evidence reference
a1a6febe-d9f3-417e-a600-43a5ed522e28
Source revision
a1336c35-9dec-4d76-83c6-55bce60a23f4
Content fingerprint
0440f5b10c0f60df7b5fcb98d7a735048b83b2dc060820fb65c519f9060d814f
Source address
https://epbcpublicportal.environment.gov.au/all-referrals/project-referral-summary/?id=b82ae61b-219d-f111-b8db-6045bde6a109

Regulatory evidence

Source reported

The portal displays project status “Referral Decision Made,” while the project description lists finalising Operational Works approvals with Ipswich City Council as a future step; neither establishes that all approvals are complete. The captured page states it is an offline, read-only version and warns that project status fields for some projects may update. The related-decisions table shows loading, permission and error messages and provides no usable decision details.

Attributed to epbcpublicportal.environment.gov.au.

Source: epbcpublicportal.environment.gov.au · publication date not recorded · observed 2026-10-17

Sources and evidence · epbcpublicportal.environment.gov.au
Source published: Not recordedObserved: 2026-10-17

epbcpublicportal.environment.gov.au
Attributed to epbcpublicportal.environment.gov.au

Technical record · The portal displays project status “Referral Decision Made,” …
Evidence location
/html/body/div[1]/div[1]/text-position:4
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
9a9ccf14-ff22-4225-a7ca-aba3118c4964
Evidence reference
42cb33a3-89c9-4762-af55-2a9b6795bc6b
Source revision
a1336c35-9dec-4d76-83c6-55bce60a23f4
Content fingerprint
0440f5b10c0f60df7b5fcb98d7a735048b83b2dc060820fb65c519f9060d814f
Source address
https://epbcpublicportal.environment.gov.au/all-referrals/project-referral-summary/?id=b82ae61b-219d-f111-b8db-6045bde6a109

Procurement

Planned

Execution of the EPC and Long-Term Service Agreement (LTSA), and execution of connection and access agreements with Powerlink Queensland for the Blackstone Substation extension and high-voltage underground cables, are listed as future steps. The description does not state that these agreements have been executed.

Attributed to epbcpublicportal.environment.gov.au.

Source: epbcpublicportal.environment.gov.au · publication date not recorded · observed 2026-10-17

Sources and evidence · epbcpublicportal.environment.gov.au
Source published: Not recordedObserved: 2026-10-17

epbcpublicportal.environment.gov.au
Attributed to epbcpublicportal.environment.gov.au

Technical record · Execution of the EPC and Long-Term Service Agreement …
Evidence location
/html/body/form/div[2]/div[2]/div/div/div/div[2]/div[2]/div[2]/div[1]/div/div/div[1]/div/div/div/fieldset[2]/table
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
0ad2e442-23fd-4d90-aa10-21b01762ec75
Evidence reference
a1a6febe-d9f3-417e-a600-43a5ed522e28
Source revision
a1336c35-9dec-4d76-83c6-55bce60a23f4
Content fingerprint
0440f5b10c0f60df7b5fcb98d7a735048b83b2dc060820fb65c519f9060d814f
Source address
https://epbcpublicportal.environment.gov.au/all-referrals/project-referral-summary/?id=b82ae61b-219d-f111-b8db-6045bde6a109

Next milestone

Planned

The project description targets financial close and issuance of the Notice to Proceed for construction in Q4 2026.

Attributed to epbcpublicportal.environment.gov.au.

Source: epbcpublicportal.environment.gov.au · publication date not recorded · observed 2026-10-17

Sources and evidence · epbcpublicportal.environment.gov.au
Source published: Not recordedObserved: 2026-10-17

epbcpublicportal.environment.gov.au
Attributed to epbcpublicportal.environment.gov.au

Technical record · The project description targets financial close and issuance …
Evidence location
/html/body/form/div[2]/div[2]/div/div/div/div[2]/div[2]/div[2]/div[1]/div/div/div[1]/div/div/div/fieldset[2]/table
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
2230707f-f96b-49a9-9d6b-ee66a77d5535
Evidence reference
a1a6febe-d9f3-417e-a600-43a5ed522e28
Source revision
a1336c35-9dec-4d76-83c6-55bce60a23f4
Content fingerprint
0440f5b10c0f60df7b5fcb98d7a735048b83b2dc060820fb65c519f9060d814f
Source address
https://epbcpublicportal.environment.gov.au/all-referrals/project-referral-summary/?id=b82ae61b-219d-f111-b8db-6045bde6a109

Financing stage

Planned

Completing project financing and achieving financial close are listed as steps to be completed following the EPBC Act referral.

Attributed to epbcpublicportal.environment.gov.au.

Source: epbcpublicportal.environment.gov.au · publication date not recorded · observed 2026-10-17

Sources and evidence · epbcpublicportal.environment.gov.au
Source published: Not recordedObserved: 2026-10-17

epbcpublicportal.environment.gov.au
Attributed to epbcpublicportal.environment.gov.au

Technical record · Completing project financing and achieving financial close are …
Evidence location
/html/body/form/div[2]/div[2]/div/div/div/div[2]/div[2]/div[2]/div[1]/div/div/div[1]/div/div/div/fieldset[2]/table
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
fa7b7fea-a4b3-426c-938b-b9463f1644bf
Evidence reference
a1a6febe-d9f3-417e-a600-43a5ed522e28
Source revision
a1336c35-9dec-4d76-83c6-55bce60a23f4
Content fingerprint
0440f5b10c0f60df7b5fcb98d7a735048b83b2dc060820fb65c519f9060d814f
Source address
https://epbcpublicportal.environment.gov.au/all-referrals/project-referral-summary/?id=b82ae61b-219d-f111-b8db-6045bde6a109
Source report history

Prior and superseded states remain labelled. Dates below identify source publication when known, otherwise source observation. They are not assumed event dates; each fact retains its own time qualifications.

  1. No material timeline events have been released.

Follow this project

Get project updates by email when new information is published.

Follow for free without an account, with the option to unsubscribe anytime. We'll email you a link to confirm.

DEEPRFP, S.L.U. uses your email and selected project to confirm and deliver the updates you request. You can stop anytime. Product news needs a separate opt-in. Read the Privacy Policy for legal bases, recipients, retention, your rights and contact details.