Project scope
Photovoltaic facility with stated installed capacity of 30.80 MW; this figure does not establish that the capacity is commissioned.
Reported status and procurement
Reported development
Listed as “În implementare” (in implementation).
Procurement availability
Unknown / not established
Reported procurement
The source reports a signed supply contract no. 161 dated 16.09.2026 with ASTRONERGY SOLAR MODULES B.V. for 51,678 photovoltaic panels and 88 inverters; delivery is stated as DDP at the site within 60 and 90 days of signing, respectively. Separately, the page labels the steel-structure supply and relaunched photovoltaic-park construction procedures as active, listing offer deadlines of 13.08.2026, 12:00 and 16.10.2026, 12:00, respectively. The earlier construction procedure was annulled after errors were identified in its specifications.
Reported financing
Financing contract no. 1170, dated 23.06.2025, is listed.
A source report alone does not establish current progress or an open buying window.
Project summary
CEF Brașov is a photovoltaic facility at Calea Feldioarei FN in Brașov Municipality, Brașov County. Its stated installed capacity is 30.80 MW, and the source lists the project as in implementation; the listed capacity does not establish commissioning. The reported total project value is 140,979,465.45 lei including VAT, with 11,461,470.64 lei shown as financed from the Modernisation Fund. The source reports a signed contract for panels and inverters. It also labels steel-structure supply and relaunched construction procedures active, with offer deadlines of 13 August 2026 and 16 October 2026, respectively. The earlier construction procedure was annulled after errors were identified in its specifications.
Evidence limits and unknowns
Commissioning and achieved operating capacity are not established; the source lists the project as in implementation.
The outcome and current availability of the steel-structure and relaunched construction procedures are not established by the supplied text. It lists offer deadlines of 13.08.2026 and 16.10.2026, respectively.
Is this project a fit for your company?
Check how this project relates to what your company supplies, with evidence gaps and a next step.
Create your account for free and include your business details to get custom commercial assessments.
Project metadata
Country
Romania Based on reviewed release evidence
Region
Europe
Category
Energy Derived from released evidence
Physical assets
Solar PV
Based on this release's supporting evidence. Unresolved fields remain unclassified; these labels do not establish current progress or a buying window.
Released facts and supporting evidence
Each fact retains its source, uncertainty and time context. If a publisher page moves or is unavailable, use the recorded quotation and observation date below.
Project name
Source reported
CEF Brașov (Centrală Fotovoltaică / photovoltaic power plant).
Attributed to www.brasovrenewables.ro.
Source: www.brasovrenewables.ro · publication date not recorded · observed 2026-10-18
Sources and evidence · www.brasovrenewables.ro
Source published: Not recordedObserved: 2026-10-18
The source reports a signed supply contract no. 161 dated 16.09.2026 with ASTRONERGY SOLAR MODULES B.V. for 51,678 photovoltaic panels and 88 inverters; delivery is stated as DDP at the site within 60 and 90 days of signing, respectively. Separately, the page labels the steel-structure supply and relaunched photovoltaic-park construction procedures as active, listing offer deadlines of 13.08.2026, 12:00 and 16.10.2026, 12:00, respectively. The earlier construction procedure was annulled after errors were identified in its specifications.
Attributed to www.brasovrenewables.ro.
Source: www.brasovrenewables.ro · publication date not recorded · observed 2026-10-18
Sources and evidence · www.brasovrenewables.ro
Source published: Not recordedObserved: 2026-10-18
Total project value: 140,979,465.45 lei including VAT. The amount shown as financed from the Modernisation Fund is 11,461,470.64 lei; the source also states that 8.12% of total investment is co-financed through the fund.
Attributed to www.brasovrenewables.ro.
Source: www.brasovrenewables.ro · publication date not recorded · observed 2026-10-18
Sources and evidence · www.brasovrenewables.ro
Source published: Not recordedObserved: 2026-10-18
Prior and superseded states remain labelled. Dates below identify source publication when known, otherwise source observation. They are not assumed event dates; each fact retains its own time qualifications.
No material timeline events have been released.
Follow this project
Get project updates by email when new information is published.
Follow for free without an account, with the option to unsubscribe anytime. We'll email you a link to confirm.
DEEPRFP, S.L.U. uses your email and selected project to confirm and deliver the updates you request. You can stop anytime. Product news needs a separate opt-in. Read the Privacy Policy for legal bases, recipients, retention, your rights and contact details.