Lighthouse Green Fuels Project

United Kingdom · Energy

In-depth research Release 1

Project scope

Plan: The described development comprises the SAF production, pre-treatment, processing and storage plant; marine infrastructure and pipelines for exporting finished product to marine or rail loading infrastructure; a biomass-fired CHP plant with electrical output up to approximately 200 MWe and additional steam production; utility pipelines, wastewater treatment and discharge, an electricity connection, an air separation unit, bulk storage for feedstock, intermediates and product, and associated and ancillary infrastructure.

Reported status and procurement

Reported development
Not established
Procurement availability
Unknown / not established

Reported regulatory context

The page identifies the application type as “Generating Stations.” It reports that the application was received on 21 September 2026 and that the project was at the acceptance stage as of the latest update. Comments were not available at that stage; receipt of the application does not mean it had been accepted for examination.

A source report alone does not establish current progress or an open buying window.

Project summary

The Lighthouse Green Fuels Project is a proposed SAF production development with processing, storage, export and utility infrastructure. Its described scope includes a biomass-fired CHP plant with electrical output up to approximately 200 MWe and additional steam for SAF production. The proposed Main Site is on the north bank of the River Tees, south of Seal Sands Road, in Stockton-on-Tees and Redcar and Cleveland, Teesside. The displayed boundaries are illustrative; the page directs readers to relevant plans and drawings for exact boundaries.

The Planning Inspectorate’s update dated 30 September 2026 says the application had been received on 21 September and was at the acceptance stage. A decision on acceptance was due by 19 October 2026; the page does not confirm that it was accepted. Comments were not available at that stage. The page names LGF Projects Limited as applicant, but does not identify it as the developer; it includes a link labelled as the developer’s website.

Evidence limits and unknowns

The supplied page does not report the outcome of the acceptance decision; the stated 19 October 2026 deadline is not confirmation of acceptance.

Exact project boundaries are not established in the supplied text; the page describes displayed boundaries as illustrative and refers readers to relevant plans and drawings.

The developer’s identity is not established by the supplied text. It identifies LGF Projects Limited as applicant and includes a developer-website link, but the linked page was not acquired or interpreted.

Financing, procurement arrangements, contract packages and purchasing timing are not stated in the project-information content supplied.

The supplied text does not expressly state the country.

Is this project a fit for your company?

Check how this project relates to what your company supplies, with evidence gaps and a next step.

Create your account for free and include your business details to get custom commercial assessments.

Project metadata

Country
United Kingdom
Based on reviewed release evidence
Region
Europe
Category
Energy
Derived from released evidence
Physical assets
Not classified

Based on this release's supporting evidence. Unresolved fields remain unclassified; these labels do not establish current progress or a buying window.

Released facts and supporting evidence

Each fact retains its source, uncertainty and time context. If a publisher page moves or is unavailable, use the recorded quotation and observation date below.

Project name

Source reported

Lighthouse Green Fuels Project

Attributed to Planning Inspectorate.

Source: Planning Inspectorate · publication date not recorded · observed 2026-10-01

Sources and evidence · Planning Inspectorate
Source published: Not recordedObserved: 2026-10-01

Planning Inspectorate
Attributed to Planning Inspectorate

Technical record · Lighthouse Green Fuels Project
Evidence location
/html/head/title
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
f4ec8be9-d4df-4ce5-9479-1dc509291d26
Evidence reference
b1cbca23-7c6a-4bca-ab89-8fa39c7b0bdc
Source revision
2e051776-84cc-4a96-b3d0-3bb6c811b200
Content fingerprint
046ee3b967798d203ad4f93400e9762046e2e72d16b6408437ac1e1da5558f3e
Source address
https://national-infrastructure-consenting.planninginspectorate.gov.uk/projects/EN0110025

Scope

Planned

The described development comprises the SAF production, pre-treatment, processing and storage plant; marine infrastructure and pipelines for exporting finished product to marine or rail loading infrastructure; a biomass-fired CHP plant with electrical output up to approximately 200 MWe and additional steam production; utility pipelines, wastewater treatment and discharge, an electricity connection, an air separation unit, bulk storage for feedstock, intermediates and product, and associated and ancillary infrastructure.

Attributed to Planning Inspectorate.

Source: Planning Inspectorate · publication date not recorded · observed 2026-10-01

Sources and evidence · Planning Inspectorate
Source published: Not recordedObserved: 2026-10-01

Planning Inspectorate
Attributed to Planning Inspectorate

Technical record · The described development comprises the SAF production, pre-treatment, …
Evidence location
/html/body/div[2]/main/div/div[2]/section[2]/p[3]
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
a2da8964-7cca-49d8-9b6d-e96ec51689ec
Evidence reference
35983942-7c5d-4672-8b3d-bcb13c1af520
Source revision
2e051776-84cc-4a96-b3d0-3bb6c811b200
Content fingerprint
046ee3b967798d203ad4f93400e9762046e2e72d16b6408437ac1e1da5558f3e
Source address
https://national-infrastructure-consenting.planninginspectorate.gov.uk/projects/EN0110025

Location

Planned

The project land is described as being in the boroughs of Stockton-on-Tees and Redcar and Cleveland, Teesside. The proposed Main Site is on the north bank of the River Tees, south of Seal Sands Road. The page says displayed boundaries are illustrative and points to the latest relevant plans and drawings for exact boundaries.

Attributed to Planning Inspectorate.

Source: Planning Inspectorate · publication date not recorded · observed 2026-10-01

Sources and evidence · Planning Inspectorate
Source published: Not recordedObserved: 2026-10-01

Planning Inspectorate
Attributed to Planning Inspectorate

Technical record · The project land is described as being in …
Evidence location
/html/body/div[2]/main/div/div[2]/p[1]
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
66db3281-fae1-4530-b96e-88979111b17f
Evidence reference
add61176-6020-4e33-8bc3-c222eeb97be3
Source revision
2e051776-84cc-4a96-b3d0-3bb6c811b200
Content fingerprint
046ee3b967798d203ad4f93400e9762046e2e72d16b6408437ac1e1da5558f3e
Source address
https://national-infrastructure-consenting.planninginspectorate.gov.uk/projects/EN0110025

Developer

Source reported

The supplied text does not identify the developer. It contains a link labelled “View the developer's website,” but the linked page was not acquired or interpreted.

Attributed to Planning Inspectorate.

Source: Planning Inspectorate · publication date not recorded · observed 2026-10-01

Sources and evidence · Planning Inspectorate
Source published: Not recordedObserved: 2026-10-01

Planning Inspectorate
Attributed to Planning Inspectorate

Technical record · The supplied text does not identify the developer. …
Evidence location
/html/body/div[2]/main/div/div[2]/section[2]/a/text-position:85
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
060e1cfc-4cc6-4406-9e62-2e381c234545
Evidence reference
fdfc483d-4bbc-44ba-a7c6-5a27916ae728
Source revision
2e051776-84cc-4a96-b3d0-3bb6c811b200
Content fingerprint
046ee3b967798d203ad4f93400e9762046e2e72d16b6408437ac1e1da5558f3e
Source address
https://national-infrastructure-consenting.planninginspectorate.gov.uk/projects/EN0110025

Regulatory evidence

Source reported

The page identifies the application type as “Generating Stations.” It reports that the application was received on 21 September 2026 and that the project was at the acceptance stage as of the latest update. Comments were not available at that stage; receipt of the application does not mean it had been accepted for examination.

Attributed to Planning Inspectorate.

Source: Planning Inspectorate · publication date not recorded · observed 2026-10-01

Sources and evidence · Planning Inspectorate
Source published: Not recordedObserved: 2026-10-01

Planning Inspectorate
Attributed to Planning Inspectorate

Technical record · The page identifies the application type as “Generating …
Evidence location
/html/body/div[2]/main/div/div[2]/section[2]/p[1]
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
d0c89c32-4ab5-4dd4-941b-1e35a87cc08d
Evidence reference
8c80ecef-7af4-4901-9fd3-85636f366659
Source revision
2e051776-84cc-4a96-b3d0-3bb6c811b200
Content fingerprint
046ee3b967798d203ad4f93400e9762046e2e72d16b6408437ac1e1da5558f3e
Source address
https://national-infrastructure-consenting.planninginspectorate.gov.uk/projects/EN0110025

Next milestone

Planned

A decision on whether to accept the application for examination was due by 19 October 2026. This is a stated deadline, not evidence that the application was accepted.

Attributed to Planning Inspectorate.

Source: Planning Inspectorate · publication date not recorded · observed 2026-10-01

Sources and evidence · Planning Inspectorate
Source published: Not recordedObserved: 2026-10-01

Planning Inspectorate
Attributed to Planning Inspectorate

Technical record · A decision on whether to accept the application …
Evidence location
/html/body/div[2]/main/div/div[2]/section[3]/p[2]
Claim confidence
0.90 on a 0–1 evidence-support scaleNot a probability of project success or procurement availability.
Claim reference
3e572e0a-b46a-4363-9e6f-8383489c6e81
Evidence reference
4a3d8faf-550e-4ec9-ac40-9a84034ecc3b
Source revision
2e051776-84cc-4a96-b3d0-3bb6c811b200
Content fingerprint
046ee3b967798d203ad4f93400e9762046e2e72d16b6408437ac1e1da5558f3e
Source address
https://national-infrastructure-consenting.planninginspectorate.gov.uk/projects/EN0110025
Source report history

Prior and superseded states remain labelled. Dates below identify source publication when known, otherwise source observation. They are not assumed event dates; each fact retains its own time qualifications.

  1. No material timeline events have been released.

Follow this project

Get project updates by email when new information is published.

Follow for free without an account, with the option to unsubscribe anytime. We'll email you a link to confirm.

DEEPRFP, S.L.U. uses your email and selected project to confirm and deliver the updates you request. You can stop anytime. Product news needs a separate opt-in. Read the Privacy Policy for legal bases, recipients, retention, your rights and contact details.