Oakland TraPac electric crane phase: four new ship-to-shore cranes at TraPac’s Oakland terminal.
United States · Transport and logistics
In-depth researchRelease 1
Project scope
Four new 100%-electric Liebherr ship-to-shore cranes, manufactured in Ireland; each is reported as 440+ feet tall, designed to reach 24 container rows and work stacks up to 11 containers high. Two were reported in service/fully operational; the other two were under construction or assembly and expected to be operational in Fall 2026.
Reported status and procurement
Reported development
Not established
Procurement availability
Unknown / not established
A source report alone does not establish current progress or an open buying window.
Project summary
A Port of Oakland update dated July 30, 2026, describes four electric ship-to-shore cranes at TraPac’s Oakland terminal. It reports that the first two had been commissioned and were operational, while the remaining two were still being built and were expected to enter service in Fall 2026. The article identifies Liebherr as manufacturer and Pacific Crane Maintenance Company as on-site assembler.
Evidence limits and unknowns
The July 2026 article does not state project cost, financing amount, or procurement route, or identify a supplier opportunity. It also does not establish the later status of the two cranes expected to enter service in Fall 2026.
Is this project a fit for your company?
Check how this project relates to what your company supplies, with evidence gaps and a next step.
Create your account for free and include your business details to get custom commercial assessments.
Project metadata
Country
United States Based on reviewed release evidence
Region
North America
Category
Transport and logistics Derived from released evidence
Physical assets
Seaport
Based on this release's supporting evidence. Unresolved fields remain unclassified; these labels do not establish current progress or a buying window.
Released facts and supporting evidence
Each fact retains its source, uncertainty and time context. If a publisher page moves or is unavailable, use the recorded quotation and observation date below.
Date
Source reported
The page is dated July 30, 2026, and the article text carries a July 28, 2026 dateline. Crane sections arrived in January 2026; a time-lapse documents construction from April–June 2026; commissioning of the first two cranes was celebrated on July 7.
Attributed to www.portofoakland.com.
Source: www.portofoakland.com · publication date not recorded · observed 2026-10-18
Sources and evidence · www.portofoakland.com
Source published: Not recordedObserved: 2026-10-18
Four new 100%-electric Liebherr ship-to-shore cranes, manufactured in Ireland; each is reported as 440+ feet tall, designed to reach 24 container rows and work stacks up to 11 containers high. Two were reported in service/fully operational; the other two were under construction or assembly and expected to be operational in Fall 2026.
Attributed to www.portofoakland.com.
Source: www.portofoakland.com · publication date not recorded · observed 2026-10-18
Sources and evidence · www.portofoakland.com
Source published: Not recordedObserved: 2026-10-18
Prior and superseded states remain labelled. Dates below identify source publication when known, otherwise source observation. They are not assumed event dates; each fact retains its own time qualifications.
No material timeline events have been released.
Follow this project
Get project updates by email when new information is published.
Follow for free without an account, with the option to unsubscribe anytime. We'll email you a link to confirm.
DEEPRFP, S.L.U. uses your email and selected project to confirm and deliver the updates you request. You can stop anytime. Product news needs a separate opt-in. Read the Privacy Policy for legal bases, recipients, retention, your rights and contact details.